The Bilcon NAFTA Arbitration: The Damages Ruling
March 1, 2019
Meinhard Doelle
The decade long legal saga over the Whites Point Quarry project in Digby Neck, Nova Scotia
appears to be finally coming to a close. For an overview of the key steps in the NAFTA
process, see https://investmentpolicyhub.unctad.org/ISDS/Details/304. The NAFTA tribunal,
which had previously found in favour of Bilcon at the liability stage of the NAFTA Chapter 11
process, recently issued its ruling on damages, awarding Bilcon only a tiny fraction of the
damages it was seeking. While Bilcon could make a last-ditch effort to apply to have the
damages finding set aside, a change in the outcome is unlikely at this point.
As I previously reported
(https://blogs.dal.ca/melaw/2015/03/25/clayton-whites-point-nafta-challenge-troubling/), the
project, initially proposed in the early 2000’s, was rejected in 2007 by both the federal and
Nova Scotia governments following an unfavourable assessment by a federal-provincial
review panel. In response, rather than challenge the decision in a Canadian court by way of
judicial review, the proponent, Bilcon, filed a $500 million damages claim under Chapter 11 of
NAFTA, alleging that as a US investor, it was unfairly treated by the review panel and by
government decision makers.
After 7 years of motions, submissions and hearings, the NAFTA tribunal, in a split decision,
agreed with the proponent on liability. Two out of the three members of the tribunal
concluded that the review panel (and the two levels of government who relied on the panel
report in rejecting the project) had not treated Bilcon fairly. They found that the panel had
erred by imposing a “community core values” test on the project without notice to the
proponent, and by failing to complete the ‘likely significant adverse effects after mitigation’
analysis required under the Canadian Environmental Assessment Act (CEAA). I previously
commented on the liability phase of the NAFTA ruling here:
https://blogs.dal.ca/melaw/2015/03/25/clayton-whites-point-nafta-challenge-troubling/. The
government of Canada sought judicial review of the finding of the NAFTA tribunal on the
basis that the panel’s work was consistent with the provisions of the applicable provisions of
the CEAA and the Nova Scotia Environment Act, but lost before the Federal Court
(https://www.italaw.com/sites/default/files/case-documents/italaw9696.pdf).
In the meantime, the NAFTA tribunal proceeded to the damages phase of its process. The
tribunal was, of course, bound by its previous ruling on liability. Essentially, having found that
Bilcon was treated unfairly as a result of the errors made by the panel, and as a result of the
two levels of government deciding to reject the project on the strength of the panel report, the
tribunal then considered what damages Bilcon had suffered as a result of the unfair treatment
it had received. The key issue for the tribunal was to determine what losses or harm the
claimant had suffered as a result of the respondent’s failure to conduct an EA process in
compliance with NAFTA.
Bilcon sought in the range of $500 million on the basis that but for the errors made by the
panel, the Whites Point Quarry project would have been approved by federal and provincial
decision makers, and the proponent would have been able to operate the quarry at a profit
over a period of 50 years. The basis for this claim was twofold. First, Bilcon argued that if you
take the errors out of the panel report, there was nothing left that provided a basis for
rejecting the project. Second, Bilcon argued that until the Whites Point Quarry, the province
of Nova Scotia had never ‘seen a quarry proposal it did not like’.
Canada took the position that even if the panel had not made the errors it did, there was no
certainty that the project would have been approved, in fact it was reasonable, based on the
evidence before the panel, to conclude that the project would still have been rejected.
Canada particularly argued that the proposed project could reasonably have been rejected by
the federal government based on significant adverse effects on whales and lobster, and by
the province of Nova Scotia based on these same adverse effects, as well as the negative
socio-economic effects of the project. Based on this, Canada argued that the claimants had
not proven any harm resulting from the errors identified by the NAFTA tribunal at the liability
stage.
The tribunal rejected Bilcon’s core contention that but for the errors made, approval of the
project was a virtual certainty. It concluded that the claimants failed to prove that the
proposed project would have been approved, or that it would have been approved on
conditions that would have made it economically viable or profitable. The tribunal went on to
consider what damages the claimants would be entitled to in light of its finding that the
claimants had failed to prove that the project would have been approved.
As a preliminary matter, the tribunal concluded that while the claimants had a general duty to
mitigate their losses, it was reasonable in the circumstances for the claimants not to seek JR
of the panel report and the government decisions to reject the project. The tribunal was
clearly reluctant to require the pursuit of a domestic remedy as mitigation measure, given that
under Chapter 11 of NAFTA, the exhaustion of domestic remedies is not a prerequisite for a
claim. The tribunal furthermore appears to have shared the claimant’s concern that even if it
was going to be successful in a JR application, the outcome would likely have been a new EA
process rather than a project approval, and given the circumstances, its project may not have
been given fair consideration in a second EA process.
The tribunal then proceeded to assess damages based on the claimants’ lost a “fair
opportunity to have their case considered and assessed” in the course of the EA process
from 2001 to 2007. Essentially, the tribunal concluded that all the proponent had was an
opportunity to have the project reviewed fairly. Its value could therefore not be assessed
assuming project approval, but would rather have to be assessed based on the value of the
opportunity at the time Bilcon applied for approval. The tribunal concludes that Bilcon is
entitled to damages based on “the value of the opportunity to have the environmental impact
of the Whites Point Project assessed in a fair and non-arbitrary manner”.
The tribunal goes on to conclude that damages, at a minimum, would be the claimants’ cost
of going through EA process, which was estimated at $5 million. This conclusion appears to
be based on the assumption that the proponent would not have spent the money to go
through the EA process if the value of the opportunity was not at least as much as the cost of
the EA process. In addition to considering the cost of going through the EA process, the
tribunal also gave consideration of the value of the business opportunity before the fate of the
project was known. Based on the limited evidence before it, in part because Bilcon had
focused on lost profits as its basis for assessing damages, not the value of the opportunity
before the EA decision, the tribunal ultimately concluded that the value of the opportunity was
$7 million.
Ultimately, while Bilcon won the initial battle on liability, it ultimately was awarded very little in
damages. Furthermore, with NAFTA due to be replaced with a new agreement that does not
include an equivalent to Chapter 11, and Canada’s trade agreement with the EU due to set
up a somewhat different process, the precedential significance of the ruling may turn out to
be minimal.