IRT - Monthly Progress Report for the Month Ending 31 August 2023

0 views
Skip to first unread message

shal...@bina-s.com

unread,
Aug 16, 2023, 10:24:06 PM8/16/23
to Shazwan (Highway) ., hssi_brtjohor, brt_...@googlegroups.com, Nasir Ibrahim, adela...@hkstrategies.com, sue.hsi...@pwc.com, Ashraf Munawwir (Infra), Sri Kanthan, Mathew Philip, R.Sambamoorthy (Railway), Nurul Farhana, nurhi...@bina-s.com

Dear All,

 

Please find attached the database for August 2023 update.

 

Kindly revert back to us latest by 22 August 2023 (12 noon). We need to submit the progress update to IRDA by 27 August 2023.

 

 

Any clarification, please contact us.

 

 

Thank you.

 

Regards,

 

SHALINEE

Planning Director

 

 

BINA SCHEDULERS SDN BHD

|*3 Two Square, Suite A-29-06, No. 2 Jalan 19/1, 46300 Petaling Jaya, Selangor Darul Ehsan, MALAYSIA |

|'Ph: +60379542462|'Fax: +60379582462|(Mobile:+60123166909|'Hotline: 1 300 80 BINA(2462)|

|*Email: shal...@bina-s.com |8Website: www.bina-s.com  |

NOTICE: This email message, including any attachments, may contain information that is confidential and/or proprietary. If you are not an intended recipient, please be advised that any review, use, reproduction or distribution of this message is prohibited. If you have received this message in error, please completely destroy all electronic and hard copies, and contact the sender at +60379542462 or mailto:shal...@bina-s.com  

 

 

 

image001.png
230831 - IMBRT Database - August 23-R00.xlsx

Sammy YE Hew

unread,
Aug 21, 2023, 9:23:25 PM8/21/23
to shal...@bina-s.com, Mathew Philip, R.Sambamoorthy (Railway), Nurul Farhana, nurhi...@bina-s.com, Shazwan (Highway) ., hssi_brtjohor, brt_...@googlegroups.com, Nasir Ibrahim, sue.hsi...@pwc.com, Ashraf Munawwir (Infra), Sri Kanthan, IRT BC

Hi Shalinee,

 

Good morning.

 

Please find attached the updated baseline progress with LHK’s input for August 2023 for your action. The progress updates are as below:

 

Row

Code

Activity

Overall Progress Updated %

371

IMBRT-17990

Development of Monthly Content Calendar and Draft Content/ Copy

60%

(From 56% increased to 60%)

Crisis Preparedness Manual

413

IMBRT-18310

Develop Crisis Preparedness Manual

 

100%

(From 90% increased to 100%)

414

IMBRT-18320

Client Review and Approval

60%

(From 0% increased to 60%)

 

Do let us know if you have any questions on this. Thank you!

 

 

Regards,

Sammy Hew

Account Executive

 

From: shalinee via BRT_Johor <brt_...@googlegroups.com>
Sent: Thursday, August 17, 2023 10:24 AM
To: 'Shazwan (Highway) .' <sha...@hss.com.my>; 'hssi_brtjohor' <hssi_b...@googlegroups.com>; brt_...@googlegroups.com; 'Nasir Ibrahim' <na...@basarharun.com>; adela...@hkstrategies.com; sue.hsi...@pwc.com; 'Ashraf Munawwir (Infra)' <ash...@hss.com.my>; 'Sri Kanthan' <s...@hss.com.my>
Cc: 'Mathew Philip' <mat...@hss.com.my>; 'R.Sambamoorthy (Railway)' <sa...@hss.com.my>; 'Nurul Farhana' <nu...@bina-s.com>; nurhi...@bina-s.com
Subject: IRT - Monthly Progress Report for the Month Ending 31 August 2023

 

External:

 

--
You received this message because you are subscribed to the Google Groups "BRT_Johor" group.
To unsubscribe from this group and stop receiving emails from it, send an email to brt_johor+...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/brt_johor/00f601d9d0b1%24d08f95c0%2471aec140%24%40bina-s.com.

LHK Submission - 230831 - IMBRT Database - August 23-R00.xlsx
Reply all
Reply to author
Forward
0 new messages