IRT - Monthly Progress Report #045 for the Month Ending 31 August 2023

0 views
Skip to first unread message

Shazwan (Highway) .

unread,
Aug 21, 2023, 10:21:58 PM8/21/23
to hssi_brtjohor, BRT_Johor, Arun Gengiah, Nasir Ibrahim, Adela Megan Willy, Sue Hsien Chong (MY), Sri Kanthan, Nur Fashiha (GeoTech), Nor Haslindah Razali (GeoTech), Firdaus (BRT Johor), Mathew Philip, Suzanna (Highway), Hakim (Rail), Arevindharaj (Railway), Norain (Railway), Puteri (Rail)
Dear All,

Please update [and highlight changes (only) in] your Monthly Progress Report (your respective portion only) and the attached appendices for the month ending 31 August 2023 and submit to us by 3.00pm, Monday 28 August 2023 for our compilation and onward submission to IRDA.
**Please condense/summarise your reports older than 3 months and remove old stories. The report should be current dated to 6 months.
 
Attached Appendices to be updated:
MPR HSS - 20230831 (please rename in your dept/company's name)
Appendix 1 - Stakeholder Matrix - please submit your updates to Syarinal
Appendix 2 - Risk Register (please review and update)
Appendix 3 - Reasons for delay - (Arun to submit the compiled updates)

Thank you.

Best regards,
Shazwan Suhaimi




HSS Integrated Sdn. Bhd.
(Associate Company of HSS Engineers Berhad)

B1 (1-4) Block B, Plaza Dwitasik,
No. 21 Jalan 5/106, Bandar Sri Permaisuri,
56000 Kuala Lumpur, Malaysia




App.3 Reasons for Delay.xlsx
App.2 Risk Register.xlsx
App.1 Stakeholder.xlsx
MPR HSS - 20230831 HSS.docx

shal...@bina-s.com

unread,
Aug 27, 2023, 9:07:56 AM8/27/23
to Shazwan (Highway) ., hssi_brtjohor, BRT_Johor, Arun Gengiah, Nasir Ibrahim, Adela Megan Willy, Sue Hsien Chong (MY), Sri Kanthan, Nur Fashiha (GeoTech), Nor Haslindah Razali (GeoTech), Firdaus (BRT Johor), Mathew Philip, Suzanna (Highway), Hakim (Rail), Arevindharaj (Railway), Norain (Railway), Puteri (Rail)

Dear Shazwan,

 

Please find attached the Aug 23 updates for your perusal.

 

 

 

Thank you.

 

 

Regards,

SHALINEE

--
You received this message because you are subscribed to the Google Groups "BRT_Johor" group.
To unsubscribe from this group and stop receiving emails from it, send an email to brt_johor+...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/brt_johor/CAO_gDMuFh0oXOQxhSpvHxRTkQ6469o4BDTVmAnqfyCeW_5T2Ow%40mail.gmail.com.

Monthly Progress Report HSS 20230831.zip

Nur Wardah Ramlan

unread,
Aug 27, 2023, 11:11:07 PM8/27/23
to Shazwan (Highway) ., hssi_brtjohor, BRT_Johor, Arun Gengiah, Nasir Ibrahim, Adela Megan Willy, Sue Hsien Chong (MY), Sri Kanthan, Nur Fashiha (GeoTech), Nor Haslindah Razali (GeoTech), Firdaus (BRT Johor), Mathew Philip, Suzanna (Highway), Hakim (Rail), Arevindharaj (Railway), Norain (Railway), Puteri (Rail), IRT BC

Dear Shazwan,

 

Please find attached Monthly Progress Report for the month of August 2023 with LHK inputs, for your onwards action.

 

Thank you.

 

Regards,

Nur Wardah Ramlan

Associate

 

nurwarda...@hkstrategies.com

M : +6011 2194 0713

GL: +603 9772 7680

 

Lumos Hill+Knowlton Strategies

Level 35, Unit 35.3 & 35.4,

Menara AIA Sentral,

No 30, Jalan Sultan Ismail,

50250 Kuala Lumpur, Malaysia.

Registered name: Hill & Knowlton (SEA) Sdn Bhd

Please read the latest version of our privacy policy on our website here.

 

 

From: 'Shazwan (Highway) .' via BRT_Johor <brt_...@googlegroups.com>
Sent: Tuesday, August 22, 2023 10:25 AM
To: hssi_brtjohor <hssi_b...@googlegroups.com>; BRT_Johor <brt_...@googlegroups.com>; Arun Gengiah <ar...@bina-s.com>; Nasir Ibrahim <na...@basarharun.com>; Adela Megan Willy <adela...@hkstrategies.com>; Sue Hsien Chong (MY) <sue.hsi...@pwc.com>; Sri Kanthan <s...@hss.com.my>; Nur Fashiha (GeoTech) <fas...@hss.com.my>; Nor Haslindah Razali (GeoTech) <hasl...@hss.com.my>; Firdaus (BRT Johor) <fir...@hss.com.my>
Cc: Mathew Philip <mat...@hss.com.my>; Suzanna (Highway) <suz...@hss.com.my>; Hakim (Rail) <ha...@hss.com.my>; Arevindharaj (Railway) <arevin...@hss.com.my>; Norain (Railway) <nor...@hss.com.my>; Puteri (Rail) <put...@hss.com.my>
Subject: IRT - Monthly Progress Report #045 for the Month Ending 31 August 2023

 

External:

 

Dear All,

 

Please update [and highlight changes (only) in] your Monthly Progress Report (your respective portion only) and the attached appendices for the month ending 31 August 2023 and submit to us by 3.00pm, Monday 28 August 2023 for our compilation and onward submission to IRDA.

**Please condense/summarise your reports older than 3 months and remove old stories. The report should be current dated to 6 months.

 

Attached Appendices to be updated:

MPR HSS - 20230831 (please rename in your dept/company's name)

Appendix 1 - Stakeholder Matrix - please submit your updates to Syarinal

Appendix 2 - Risk Register (please review and update)

Appendix 3 - Reasons for delay - (Arun to submit the compiled updates)

 

Thank you.

 

Best regards,
Shazwan Suhaimi

 

 

Image removed by sender.

 

HSS Integrated Sdn. Bhd.

(Associate Company of HSS Engineers Berhad)

 

B1 (1-4) Block B, Plaza Dwitasik,

No. 21 Jalan 5/106, Bandar Sri Permaisuri,

56000 Kuala Lumpur, Malaysia

 

 

 

 

Image removed by sender.

MPR HSS - 20230831 HSS_LHK.docx

Shazwan (Highway) .

unread,
Aug 28, 2023, 9:32:32 PM8/28/23
to hssi_brtjohor, BRT_Johor, Dhanapal (Structure), Asmadi Bin Kadir (M&E), Syarinal Putra HSSI, Arun Gengiah, Nasir Ibrahim, Adela Megan Willy, Sue Hsien Chong (MY), Sri Kanthan, Nur Fashiha (GeoTech), Nor Haslindah Razali (GeoTech), Firdaus (BRT Johor), Mathew Philip, Suzanna (Highway), Hakim (Rail), Arevindharaj (Railway), Norain (Railway), Puteri (Rail), IRT BC, Nur Wardah Ramlan, Toong Yee Min (Structure)
Dear All,

Thank you for your updates for the Monthly Progress Report for month ending 31 August 2023 :
- CGB Consultants
- Geotech Dept
- Infra Dept
- LHK
- Bina-S
- Veritas

For those who are yet to provide any updates, please do so latest before 3.00 today, 29 August 2023.

Thank you.

Best regards,
Shazwan Suhaimi



Firdaus (BRT Johor)

unread,
Aug 28, 2023, 11:19:25 PM8/28/23
to Shazwan (Highway) ., hssi_brtjohor, BRT_Johor, Dhanapal (Structure), Asmadi Bin Kadir (M&E), Syarinal Putra HSSI, Arun Gengiah, Nasir Ibrahim, Adela Megan Willy, Sue Hsien Chong (MY), Sri Kanthan, Nur Fashiha (GeoTech), Nor Haslindah Razali (GeoTech), Mathew Philip, Suzanna (Highway), Hakim (Rail), Arevindharaj (Railway), Norain (Railway), Puteri (Rail), IRT BC, Nur Wardah Ramlan, Toong Yee Min (Structure)
Salam Shazwan,

Please find attached the draft of progress report for Systems for your reference (page 41) .

Rowena - please review and amend (if any)

Thanks & Regards
MPR HSS - 20230831_SYSTEMS.docx
Reply all
Reply to author
Forward