Very roughly, this particular assignment would have taken maybe 2 long
working days, using the 2 machines I have available to me.
Respower finished the rendering last night in about 4~6 hours. I just
couldnt access their FTP to grab my frames.
What I did today was render at a lower res (1280 x 720 > 640 x 360),
using my notebook and another desktop. That was maybe 1 work day.
Example frames:
1177.png took ~13 sec. (transparency slowed it down a lot)
3094.png was probably ~ 8 sec.
I'm quite inefficient in some ways.
For example I allocate a fixed number of frames per "step" in the
video (for easy planning), even though in final video editing some
steps will be sped up.
I'm quite ready to spend the money to render the redundant frames,
since it's relatively affordable for us (compared to spending human
time)
I also need the rendering / editing stages to be fast and fuss-free,
since I usually dont have much time for amendments.