Any word on including Hausman within a scheduled capital improvement project?
Best Regards,
Robert
Robert Davidson wrote:I was poking around on sanantonio.gov and found three projects for
Hausman Road
Dstrct Year Street From To
8 2008/9 S Hausman Rd Bamberger Trl Prue Rd
8 2008/9 W Hausman Rd Babcock Rd Woller Rd
8 2008/9 W Hausman Rd Woller Rd N Loop 1604 W Access Rd
Could any of these include adding bike lanes or striping?
Note that I am talking about the importance of Hausman as a bicycle corridor tonight at the Bicycle Mobility Advisory Committee meeting and would really like to include information about what the right approach would be to get bicycle related improvements on the schedule.
Best Regards,
Robert Davidson
Liza C Meyer wrote:I have left a voicemail with Ernest De La Rosa to contact me directly to assess the potential to include Hausman within a scheduled capital improvement project.
From: Christina Cruz
Sent: Wednesday, March 25, 2009 2:38 PM
To: 'rob...@davidson.name'
Cc: Liza C Meyer; Althea Montez
Subject: RE: Hausman Road
Dear Mr. Davidson,
I was informed by the Department of Public Works that Liza Meyer with the office of Environmental Policy is the temporary hike and bike coordinator. I have cc’d her on this chain letter.
If you have any questions, please contact our office.
Thank you,
Christy Cruz
District 8
From: Robert Davidson [mailto:rdavid...@satx.rr.com]
Sent: Thursday, March 19, 2009 11:30 PM
To: Christina Cruz
Cc: rob...@davidson.name; Althea Montez
Subject: Re: Hausman Road
Ms. Cruz,
How can we follow the planning of the Fredricksburg Rd project and get Hausman Road queued up for the next round of projects?
My understanding is that Abigail Kinnison resigned from the Bicycle Coordinator position in July 2008. The city posted an opening in January 2009, but has not selected any of the candidates or reposted. Is she really the right person to contact?
Thanks,
Robert
_______________________________________________________________________________________________________________________________
Christina Cruz wrote:Dear Mr. Davidson,
Here is the information regarding the project that the city is working on between downtown and the Medical Center which will have hike and bike amenities.
Project Status:
PRE-DESIGN
Estimated Construct Start:
01/2011
Estimated Construction Completion:
11/2011
Project Scope
Fredericksburg Rd Congestion Mitigation
Address congestion between the downtown business district and the South Texas Medical Center through performance of a detailed traffic analysis and requisite operational improvements (including traffic signal system upgrades, intersection geometric improvements and communication network improvements) and hike and bike amenities. The total cost for this project is currently estimated to be $39 million, with the City’s share expected to equal approximately 26% of this total.
I have attached the email that was sent to our office regarding Hausman Road and the Bicycle Master Plan for your review. If you have any questions you may contact Abigail Kinnison who can answer any and all your questions.
Thanks!
Christy Cruz
District Director for Councilwoman Diane Cibrian
District 8
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------
From: Abigail Kinnison
Subject: RE: Hausman Road Development
As committed by the passage of the Bicycle Master Plan (Ordinance 100741 - April 21, 2005), the San Antonio City Council committed to consider the provision of bicycle facilities (see attached Bicycle Facility Design Guide for definitions) for every planned roadway project. This includes roadway construction and maintenance projects as well as opportunities for re-striping of roadways. Every capital improvement project is considered for the provision of bicycle facilities at the time the project is scoped. In the case that bicycle facilities cannot be accommodated for the reason of cost or limited right-of-way, justification should be discussed and documented for future reference. In addition, every accommodation shall be made to identify, list and not preclude opportunities for future bicycle facilities, should additional funding become available.
It is not realistic to add bicycle facilities to every roadway however; priority shall be given to roadways that are located along a recommend bicycle corridor (map included in the BMP). Or that meet one or more of the following criteria:
• Proximity to a current or funded bicycle facility, and providing connection
• Proximity to a VIA Transit Route
• Proximity to a school or university
• Proximity to a park (especially those that include bicycle recreation opportunities) or linear creekway
• Proximity to a library or community center
• Proximity to shopping centers
As your letter thoughtfully suggests, Hausman Road does fit many, if not all, of these priority criteria. Unfortunately it is not currently slated for any improvements. Another goal of the BMP is: Institutionalize Bicycling in San Antonio. One of the objectives to achieving that goal is establish a full time bicycle coordinator. Abigail Kinnison of the Public Works Department has filled that position since March 2005. If you have further questions regarding the Bicycle Master Plan you may contact her directly at 207-3971.
From: Davidson, Robert [mailto:Robert....@usaa.com]
Sent: Thursday, March 19, 2009 2:48 PM
To: Christina Cruz
Cc: rob...@davidson.name
Subject: Hausman Road
Christina,
Many thanks for you time this morning! Please send me information on the plans for Hausman Road and Medical Center improvements. If you would reply all so that the information arrives at my home address as well, I would appreciate it.
As soon as I get this information I will add it (or links to it) on BikeNWSanAntonio, the Google group I am setting up to disseminate information. The current map looks like this: http://tinyurl.com/hausman
Best Regards,
Robert Davidson
Dear Mr... Davidson,I wanted to forward the response I received from Ernest De La Rosa regarding bike lanes on Hausman. A city bond needs to pass in order to widen Hausman Road, so that can be many years from now. If you have any questions, please contact our office.thanks!Christy CruzDistrict 8Christy,This section of Hausman is not wide enough for bike lanes. This type of project would have to be included when Hausman is widen, which I don't know when that will be.
From: Robert Davidson [mailto:rdavid...@satx.rr.com]
Sent: Friday, May 01, 2009 5:45 AM
To: Liza C Meyer; Ernest De La Rosa
Cc: Christina Cruz; Althea Montez; bike...@googlegroups.com
Subject: Re: Hausman Road