Sitework – 15 hrs
Grading – measure site area for grading
Storm sewer – linear feet of pipe and count structures
Water – same as above
Sewer – same as above
Gas – same as above
Hardscape –
area of asphalt pavement,
area of concrete sidewalks,
area of concrete slabs, pavers
Linear feet of curbs and gutter
Landscapping, count and sf of trees, grass, shrubs and irrigation
Electrical – count light fixtures
Athletic fields – separate by component
Academic Building – 75 hrs
3-Concrete
Foundations – cy of foundations
Retaining walls - sf
Slab on grade – sf
Elevated slabs – sf
Concrete columns – cy
Topping slab – sf (over metal deck)
4-Masonry
CMU – sf
Brick – sf
Precast or castone pieces – by lf or sf
5-Steel
Metal deck – sf (separate roof from slabs)
Beams – sf
Joists – sf
Miscelleous – sf
6-Carpentry
Base cabinets – lf
Wall cabinets – lf
Cabinet top – sf, different types
Base and crown – lf
Rough carpentry and blocking – sf
7 – Moisture & Thermal
Look for notes relating to waterproofing
Fireproofing - sf
8-Doors and Windows
Wood doors
Metal doors
Glass doors
Exterior glazing (windows and storefront)
Interior glazing (windows & storefront)
9-Finishes
Drywall
sf of interior walls
sf of exterior walls
sf of drywall ceilings
sf of acoustical ceilings
Paint – sf – CMU, drywall walls, drywall ceilings
Tile – wall, floor and base
Watch for porcelain/ceramic/terrazzo or marble tile
Flooring
10-Specialties and accessories
11-Furniture
14-Conveying
15&16-MEP’s
Haytham M. Gebara
President
NACMC