Fwd: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder

19 views
Skip to first unread message

Sanyum Gupta

unread,
Mar 27, 2014, 10:36:11 AM3/27/14
to balmukunda_residen...@googlegroups.com
Hello Fellow Future Residents,

Nice share by Jitin. Please keep sharing more information and pictures as we are near completion. Also if you know someone who owns a flat in Balmukunda and not part of this group can reply with his/her email address at balmukunda_residen...@googlegroups.com

Obtaining possession can be a pain, but if we unitedly share information and take collective decision, we can protect our hard earned money which we have invested in this project  

Regard
Sanyum

Your Group administrator

---------- Forwarded message ----------
From: jitin rao <jiti...@rediffmail.com>
Date: Thu, Mar 27, 2014 at 9:11 AM
Subject: Re: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder
To: balmukunda_residen...@googlegroups.com, pul...@gmail.com, titasht...@gmail.com, sing...@yahoo.co.in
Cc: sanyu...@gmail.com, nimmi....@gmail.com


Snaps attached

On Thu, 27 Mar 2014 19:29:04 +0530 wrote

Dear All,

This is reference to "Offer of Possession" being issued by Builder at RNE alongwith Account summary annexure being circulated for Full & Final Settlement of account .

Recently I had also recvd. this letter but to my surprise there has been no mention by Builder on account of Delay in Possession as was cited during BBA, since Project is already delayed by 3 months and in current scenario I don't see it will actual possession before July-Aug'14 taking into consideration actual site scenario when I visited on 23rd Mar'14.

On the contrary Builder has been clever and quick wittes in calculating interest on Delay in Payment on part of owner ,but it is not at all justified as there has been no such intimation by Builder regarding payment delay during entire period while issuing demand letters under CLP to owners and finally an amount has been inculcated your account.

Post visiting Project Site on 23rd Mar'14 ,I was surprised as builder will require another 3-4 months atleast to come anywhere near actual possession.(Snaps attached.)

Looking forward to hear from you all and decide on further course of action .

Regards,
Jitin Rao
8826522777

Get your own FREE website, FREE domain & FREE mobile app with Company email.  
Know More >

IMG-20140323-WA019.jpg
IMG-20140323-WA022.jpg
IMG-20140323-WA024.jpg
IMG-20140323-WA018.jpg
IMG-20140323-WA012.jpg
IMG-20140323-WA008.jpg

sachin bansal

unread,
Mar 27, 2014, 1:26:55 PM3/27/14
to balmukunda_residen...@googlegroups.com
Dear Friends

May I know who all ( flat owners of UGF) have been asked extra amount to be paid to builder towards extended balcony area????

And How much amount has been paid by the affected owners???

please update for benefit of one and all....

further, I am not aware whether is it necessary to pay advance of maintenance charges for two years??

please revert soon

regards

Sachin Bansal
B-02





--
You received this message because you are subscribed to the Google Groups "Balmukunda_Residency_RNE_Flat_owners" group.
To unsubscribe from this group and stop receiving emails from it, send an email to balmukunda_residency_rne...@googlegroups.com.
To post to this group, send email to balmukunda_residen...@googlegroups.com.
Visit this group at http://groups.google.com/group/balmukunda_residency_rne_flat_owners.
For more options, visit https://groups.google.com/d/optout.

Sanyum Gupta

unread,
Mar 27, 2014, 11:45:22 PM3/27/14
to sachin bansal, balmukunda_residen...@googlegroups.com

Sachin,
Its a norm for builder to collect maintainance charges in advance at the time of possession. Builder will provide maintainance till RWA is not form and handed over.

I have not seen my demand letter yet, but i am thinking of paying the dues realated to cost of flat and maintainace charges or any other component not related to cost of flat at the time of actual possession.

Any thoughts ?

Thanks
Sanyum

jiti...@rediffmail.com

unread,
Mar 28, 2014, 12:31:21 AM3/28/14
to balmukunda_residen...@googlegroups.com, sachin bansal
I do buy this point as there no clear picture as of now by when will we be given actual possession, however builder has calculated maintainance charges from 1st Jul'14 as per demand letter issued to me .
Sent from BlackBerry® on Airtel

From: Sanyum Gupta <sanyu...@gmail.com>
Date: Thu, 27 Mar 2014 22:45:22 -0500
To: sachin bansal<ltsachi...@gmail.com>
Subject: Re: [balmukunda_residency_rne_flat_owners:100] Fwd: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder

Nirbhai Khare

unread,
Mar 28, 2014, 2:11:12 AM3/28/14
to balmukunda_residen...@googlegroups.com, sachin bansal
Dear All,
In my opinion two things need to be resolved urgently
1. Interest which has been calculated on delay in instalment payments. Buildeer has never informed about accrual of interest amount till offer of possession letter. They should have alarmed from time to time.
They are also not mentioning anything about delay on their part in delivery of flats.
2.Builders should demand maint advance at the time of delivery only.

Pl share your views.

regards,
Kiran Khare
Regards,
NK.Khare

divya choudhary

unread,
Mar 28, 2014, 3:50:19 AM3/28/14
to balmukunda_residen...@googlegroups.com
Hello everyone,

Hopefully, soon i will be the resident of A-19 flat. I have received the possession letter and its in the agreement that we have to pay the maintenance charges but nothing is present regrading the time period and amount. The builder is asking us to pay approx. 51,000 for two years maintenance and 25,000 for the electricity connection. 

Isn't  the amount quite much???  

secondly, it was in the agreement that the builder will pay 5 rs/ sq ft/ pm for the delay after December 2013, but nothing is present in the possession letter related to it.  please give your views on the same.

Thanks
Divya 


On Fri, Mar 28, 2014 at 9:15 AM, Sanyum Gupta <sanyu...@gmail.com> wrote:

Deepak Gupta

unread,
Mar 28, 2014, 3:12:10 AM3/28/14
to balmukunda_residen...@googlegroups.com, sachin bansal
Dear All,

1)  To the best of my market knowledge, in most societies Advance maintenance is paid in advance for 2 years, but then why is there a separate component of IFMS charges. One of these two components i.e.,  either Advance Maintenance (INR 1.8 per ft per month for two years) or IFMS charges (INR 30/- per ft) should be applicable; and NOT BOTH.

2)  Electricity charges are very high (INR 28000/-), while it takes ~INR 5000 to take a meter connection.

3)  This entire payment (along with 5% basic cost) should have been asked at the time of possession only i.e., at least 90 days from now in July'14, when flats are ready for possession.

As per the discussion with GOWO, they said they are are going to have a word with MD - Meenal Housing to discuss the above issues; and asked me to wait for making the payment, till their revert.

Further, as per the discussion with the Builder (Nikhil - Finance); they advised to come to their office and have negotiation on the  final amount payable, where Interest cost and other charges can be negotiated. It does reflect an unfair play by the builder.

I suggest, we should better wait for making any payment till clarity is obtained on all of the above points and firm reply from GOWO/Builder.

Best regards,
Deepak Gupta
Flat: B-35
Mob: 9891507272


On Fri, Mar 28, 2014 at 9:15 AM, Sanyum Gupta <sanyu...@gmail.com> wrote:



--
Warm regards,
Deepak Gupta
09891507272

vinay kesarwani

unread,
Mar 28, 2014, 1:06:52 AM3/28/14
to balmukunda_residen...@googlegroups.com
Dear All
               Builder can not hand over the flats to flat owner without obtaining occupancy certificate from GDA. We should ask the builder to obtain occupancy certificate from GDA before asking for payment. Since the builder has not intimated for delayed payment, therefore we should not pay any delayed interest and jointly protest before Builder.
 
Vinay Kesarwani
9999884583


Arvind Yadav

unread,
Apr 1, 2014, 5:44:29 AM4/1/14
to balmukunda_residen...@googlegroups.com
I agreed will all occupants regarding interest calculation and advance maintenance charges. 
Builder never remind us regarding delay payment and builder had calculated delay payment interest from the date of issue of demand letter however many of occupants like me received demand letter after 5 to 6 day from the date of issue demand letter. I have leaved in Jabalpur (M.P.).
We should protest interest amount and advance maintenance charges at this time. we should pay advance maintenance charges at the time of actual possession. Why builder earn interest on our money for four to six month.Electric meter charges also very high. please update me about your views.


Kind regards,


Arvind Yadav
Ownwer of Flat no. A-89
09424314118

Sanjeev Sharma

unread,
Apr 1, 2014, 12:38:33 AM4/1/14
to balmukunda_residen...@googlegroups.com
Dear All

My self Sanjeev Sharma from (B-79). Builder also demand us for Last Installment charges....

Sanjeev Sharma
Flat No. B-79
9871056303, 9871056304


--
You received this message because you are subscribed to the Google Groups "Balmukunda_Residency_RNE_Flat_owners" group.
To unsubscribe from this group and stop receiving emails from it, send an email to balmukunda_residency_rne...@googlegroups.com.
To post to this group, send email to balmukunda_residen...@googlegroups.com.
Visit this group at http://groups.google.com/group/balmukunda_residency_rne_flat_owners.
For more options, visit https://groups.google.com/d/optout.



--
Sanjeev Sharma
9871056303

Rohit Sharma :)

unread,
Mar 31, 2014, 5:07:17 AM3/31/14
to balmukunda_residen...@googlegroups.com
HI All ,

Please share the response of GOWO  if received .

jiti...@rediffmail.com

unread,
Mar 31, 2014, 6:23:30 AM3/31/14
to balmukunda_residen...@googlegroups.com, sachin bansal
Hi All,

Would request your suggestions on final payment to be done , so as to take a collective decision finally.


------Original Message------
To: balmukunda_residen...@googlegroups.com
To: sachin bansal
Subject: Re: [balmukunda_residency_rne_flat_owners:100] Fwd: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder
Sent: Mar 28, 2014 10:01 AM

I do buy this point as there no clear picture as of now by when will we be given actual possession, however builder has calculated maintainance charges from 1st Jul'14 as per demand letter issued to me .

------Original Message------
From: Sanyum Gupta
Sender: balmukunda_residen...@googlegroups.com
To: sachin bansal
Cc: balmukunda_residen...@googlegroups.com
ReplyTo: balmukunda_residen...@googlegroups.com
Subject: Re: [balmukunda_residency_rne_flat_owners:100] Fwd: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder
Sent: Mar 28, 2014 9:15 AM

Sachin, Its a norm for builder to collect maintainance charges in advance at the time of possession. Builder will provide maintainance till RWA is not form and handed over.
I have not seen my demand letter yet, but i am thinking of paying the dues realated to cost of flat and maintainace charges or any other component not related to cost of flat at the time of actual possession.
Any thoughts ?
Thanks Sanyum
On 27-Mar-2014 12:26 pm, sachin bansal <ltsachi...@gmail.com> wrote: Dear Friends May I know who all ( flat owners of UGF) have been asked extra amount to be paid to builder towards extended balcony area???? And How much amount has been paid by the affected owners??? please update for benefit of one and all.... further, I am not aware whether is it necessary to pay advance of maintenance charges for two years?? please revert soon regards Sachin Bansal B-02 On Thu, Mar 27, 2014 at 8:06 PM, Sanyum Gupta <sanyu...@gmail.com> wrote: Hello Fellow Future Residents, Nice share by Jitin. Please keep sharing more information and pictures as we are near completion. Also if you know someone who owns a flat in Balmukunda and not part of this group can reply with his/her email address at balmukunda_residen...@googlegroups.com Obtaining possession can be a pain, but if we unitedly share information and take collective decision, we can protect our hard earned money which we have invested in this project   Regard Sanyum Your Group administrator ---------- Forwarded message ---------- From: jitin rao <jiti...@rediffmail.com> Date: Thu, Mar 27, 2014 at 9:11 AM Subject: Re: Snaps_balmukunda_residency_rne_flat_owners: Regarding Offer of Possession and Delay Penaly on Builder To: balmukunda_residen...@googlegroups.com, pul...@gmail.com, titasht...@gmail.com, sing...@yahoo.co.in Cc: sanyu...@gmail.com, nimmi....@gmail.com Snaps attached On Thu, 27 Mar 2014 19:29:04 +0530 wrote Dear All, This is reference to "Offer of Possession" being issued by Builder at RNE alongwith Account summa

hemant bhatnagar

unread,
Apr 6, 2014, 8:41:27 AM4/6/14
to balmukunda_residen...@googlegroups.com
Dear all,

As pointed out by Sh. Deepak, separate negotiation by the builder with
the flat owner is somewhere reflects shortcomings at their end for
sure. We should take up & involve GOWO who has charged hefty sum from
the flat owner to safeguard their interest. Possession letters should
not be issued without the clearance from GOWO and clearance
certificate/completion certificate from GDA. GOWO can not act as a
mute spectator. They should be made responsible for all this. Charging
Adv. maintenance and hefty amount of Rs.28,000 in the name of
electricity connection is not fare.

United we stand divided we fall, pl. note.

Regards
Hemant-A-710 ( BMR ).

On 3/28/14, Deepak Gupta <deepa...@gmail.com> wrote:
> Dear All,
>
> 1) To the best of my market knowledge, in most societies *Advance
> maintenance* is paid in advance for 2 years, but then why is there a
> separate component of *IFMS charges*. One of these two components i.e.,
> either Advance Maintenance (INR 1.8 per ft per month for two years) or
> IFMS charges (INR 30/- per ft) should be applicable; and NOT BOTH.
>
> 2) *Electricity charges* are very high (INR 28000/-), while it takes ~INR
> 5000 to take a meter connection.
>
> 3) This entire payment (along with 5% basic cost) should have been asked
> *at
> the time of possession only* i.e., at least 90 days from now in July'14,
> when flats are ready for possession.
>
> As per the discussion with GOWO, they said they are are going to have a
> word with MD - Meenal Housing to discuss the above issues; and asked me to
> wait for making the payment, till their revert.
>
> Further, as per the discussion with the Builder (Nikhil - Finance); they
> advised to come to their office and have negotiation on the final amount
> payable, where* Interest cost and other charges can be negotiated*. It does
>>> <http://sigads.rediff.com/RealMedia/ads/click_nx.ads/www.rediffmail.com/signatureline.htm@Middle?>
>>> Get your own *FREE* website, *FREE* domain & *FREE* mobile app with
>>> Company email.
>>> *Know More
>>> >*<http://track.rediff.com/click?url=___http://businessemail.rediff.com/company-email-hosting-services?sc_cid=sign-1-10-13___&cmp=host&lnk=sign-1-10-13&nsrv1=host>
>> To post to this group, send email to
>> balmukunda_residen...@googlegroups.com.
>> Visit this group at
>> http://groups.google.com/group/balmukunda_residency_rne_flat_owners.
>> For more options, visit https://groups.google.com/d/optout.
>>
>
>
>
> --
> Warm regards,
> Deepak Gupta
> 09891507272
>
> --
> You received this message because you are subscribed to the Google Groups
> "Balmukunda_Residency_RNE_Flat_owners" group.
> To unsubscribe from this group and stop receiving emails from it, send an
> email to balmukunda_residency_rne...@googlegroups.com.
> To post to this group, send email to
> balmukunda_residen...@googlegroups.com.
> Visit this group at
> http://groups.google.com/group/balmukunda_residency_rne_flat_owners.
> For more options, visit https://groups.google.com/d/optout.
>


--
Hemant Bhatnagar
IRCTC

Umesh Kumar Sharma

unread,
Apr 7, 2014, 3:51:52 AM4/7/14
to balmukunda_residen...@googlegroups.com
Dear All
Hello
In my view Mr. Vinay Kesarwani has pointed out correctly that before obtaining the occupancy certificate or completion certificate from GDA, builder can not issue the "Offer of Possession" to flat owners. I am trying to obtain a copy of the ordinance issued by GDA in connection of completion certificate/ Occupancy certificate.
About delayed payment interest, since there was no prior intimation given by builder, we very well can refuse for.
In the demand letter builder has always mentioned that ''payment to be made within 10 days of issuing the latter" but the legal language is supposed to be '' Payment is to be made within 10 days of receiving the latter".
There will be so many things of such lapses on the part of the builder, which can be easily challenged in the District Consumer forum and it will be more fruit full if done collectively.

Thanks N Warm Regards
Umesh Sharma
B 78
9711598330