Dear member,1. Regarding offer of possession it has been informed that till date 18 members have already made full and final payment and 10 members have made part payment.2. Remaining members are suggested to visit the project site to see the progress at their convenience For any assistance members may contact GOWO Office at SF-30, Ansal Fortune Arcade, Sector - 18, NOIDA - 2010301.3. GOWO team had joint inspection of the project site with the management of Meenal Group on 26 Apr 2014 and some of the question frequently asked by the members are answered by the builder as follows:-.Thanks & Regards,
A ChaudhryGOWOUG-47&48Ansal Chamber-IIBikhaji Cama PlaceNew Delhi - 66(M) 8826000227Email: no...@gowo.co.inWebsite : www.gowo.co.in
------------------------------------------------------------------------------------------------------------------- Forwarded message ----------
From: Meenal Housing(P) Ltd. <salesmee...@gmail.com>
Date: Thu, May 1, 2014 at 1:59 PM
Subject: Fwd: Joint Site Inspection
To: Ashok Chaudhry <acha...@gowo.co.in>, Project Director <no...@gowo.co.in>
Dear Sir,
1. Please refer to our joint site inspection on 26 Apr 2014 at 4 PM of RNE Project. Your appreciation has encouraged us to complete the remaining work with more perfection and speed.
2. In all probability project will be completed in time. Other details of our project is as follows:-
(a) Compounding: - The compounding of our project has already been taken from the concerned authorities.
(b) Fire Fighting: - All arrangement of fire fighting has been installed and completed. NOC received from the department.
(c) Electricity Connection: - We have already been sanctioned the electricity connection of 1000 KWA bulk load.
(d) Drinking Water arrangement: - Water softening plant has already arrived at site and is under installation. Hope the same will be completed soon.
3. Above details are for your information.
Thanking You
Your Sincerely
Anuj Mehrotra
Director
Meenal Housing Pvt.Ltd