--From: Sharad JatiaDear All,On July 31st, I had been to Zonal Office [ zone VII ] of Corporation of Chennai and metMiss Nilavazhagi, Assistant Engineer and expressed my dissatisfaction on the bad
condition of Padikuppam Road.Feedback received from her is given below :" Sir we are ready to lay the road and also remove the enroachments . CMWSSB
Metro Water has to complete the sewerage work. We have aslo send a letter to
their Chindadripet office but no reply has come so far. You should inter act withEE -Mr. Ambalavanam and / or Mr.Anandan-AEE. After the sewerage work is over
road work will be taken up immediately "
She was very cooperative.I then spoke to Mr Ambalavanan and he directed me to Mr. Anandan. Today when
I spoke to Mr. Anandan, he said that Padikuppam Road is a bus route roadand view of so many complaints received from individuals, he has directed theCorporation to start the road work immediately. On enquiring about the pending
sewerage work, he said we shall see later.
Let us all wait for another 15 days and in case no action is taken by the
corporation I shall personally go the the Chindadripet office of Metro Water and
meet both the officials and give a further feedback.
Regards : Sharad Jatia
You received this message because you are subscribed to the Google Groups "Balaji Nagar" group.
To unsubscribe from this group and stop receiving emails from it, send an email to balaji-nagar...@googlegroups.com.
To post to this group, send email to balaji...@googlegroups.com.
Visit this group at http://groups.google.com/group/balaji-nagar.
For more options, visit https://groups.google.com/d/optout.
Sir thanks for the update