"Pls see attached photos that i took yesterday during Axis Crown viewing. Common area definitely not complete yet.
E-36-01 : the person incharge said that your unit is 70% finish, but to be honest i feel only 30-50%. Tiles and the paint still undercoat, the tiles for balcony is not fix yet and they're still do some finishing on the wall tiles. The concrete wall and structure looks ok, no hair crack detected. But tile finishing... really need to be changed during renovation.
Some of the unit in the E-25 floor, Leong said nearly 100% completed, but as u can see fr the photo just 70% and a lot of part need to re-painting.
When i asked on the handover date, Leong still can't estimate the complete date."
Looks like more patience needed!!! Lots more!!! I will post the photos but not until probably the weekend.
Andrew