- We will be providing the covered car park for your apartment, however, the agreement will mention 1 car park only, as it is a standard draft for all our members.
- We will not be able to make any changes in the same. Approval shall be on case to case basis and as per the discretion of the management.
- As of now, there are no betterment charges payable. However, if it becomes applicable in near future, then the same needs to be paid by the member only.
- We will let you know well in advance for registration. If there is a genuine reason for delay, management will provide the grace period as per its discretion.
- Any major changes/deviations shall be informed to the members.
- The clause refers to force majeure conditions, which cannot be predicted. In any case, the developer will always try and complete the project, as it involves a huge investment from his end also.
- The clause is as per the general market practise only and as per our company’s standard policy. We will not be able to make any changes in the same.
- If there is any variation in the area, the amount will accordingly be adjusted at the time of execution of final sale deed.
- The amenities/facilities are mentioned in the brochure for your reference. We will not be able to incorporate the same in the agreement.
- Regarding the OC, it will also require the editing of draft, which will not be possible. However, please be assured that we have been following and will follow all the necessary government guidelines and procedures required for our schemes.
- The possession of the apartment shall be given starting from December-2017. The March-2018 is the completion date in all aspects. The grace period has, therefore, been kept from March-2018.
- The clause is as per the general market practise only and as per our company’s standard policy. We will not be able to make any changes in the same.
- The undivided share of land shall be mentioned once the hard copy of agreement is received by us. It will be mentioned in the blank space left in Clause E and Schedule B manually. You will need to put your initial signature against the clause beforehand and our authorized signatory will manually enter the same and cross sign it. The undivided land area for your flat is 229 sq. ft.
- We are only mentioning the saleable area in the agreement.
Regards,
Jyotsna
From: Vipul Parmar <vipulpar...@gmail.com>
To:
Date: 09/03/2015 13:39
Subject: Re: Updated Agreement of A-503
Sections | |
2 | Covered Car parking is not mentioned in the agreement. Only car parking is mentioned |
5.2 | Agreement clause states that, purchaser is not supposed to install any additional AC units/points. Since Additional points can be installed with prior approval of developer, kindly change the clause accordingly. |
5.9 | It states that we need to pay betterment charges to BBMP in future if applicable. Since we have invested in this project knowing this is an "A Khata" property there is no need to mention this clause in the agreement. But if there is any ambiguity regarding "KHATA", it should be known to us. |
5.10 | Grace period for registration It should be mentioned in the agreement that for genuine reasons such as - Buyer may be based out of India etc. grace period can be extended beased on management decision. |
6.1 | Change in Specifications If there is any change in the amenities or fixtures because of requirement form architect or engineers, Buyer should be informed in advance |
9 | Please mention specific Conditions like "Force Majure" under which the project will get cancelled |
11.2 | Breach of contract : Termination Agreement states termination if breach of contract by buyer. It should also mention the same about Developer |
15.2 | Variation in SBA Agreement should mention that if there is a variation of 5% or more in SBA, the cost will be adjusted according(up or down). |
| Amenities Specific amenities to be provided is not mentioned in the agreement. How do we make sure that whatever amenities was advertised, will be provided if it is not mentioned in the agreement | |
| Occupancy Certificate There is no mention of the OC in the agreement. | |
3.2 | Project completion date During pre-launch offer,Builder informed that project will be completed in 3 years time(i.e. June -2017). As per agreement its now on March-2018 with 6 months grace period. It means project will be completed by Sept-2018 considering current status of construction. As I booked it during pre-launch offer(i.e. between Feb-14 to June-14) will have to wait for nearly 4.5 years which is unacceptable. Hence for me project completion date must be kept as June-17 and change penalty applicable date accordingly. |
3.3 | Delay from both side Penalty clause is biased to builder. 3rs/sqrt from builder side which is very less compared to standards followed by other well-known builders. It should be 8rs/sqrt. If builder is not agreeing to reduce it than penalty from buyer side must be reduced from 16% to 10% |
| There is no mention of Undivided share for our unit in the agreement | |
| No carpet area mentioned in the agreement |
Please clarify some issues in
the Draft Agreement you have sent.
1. What is the undivided share of land I get for
my Flat C-104?
A) The undivided land area for your flat is 308 sq. ft. It will be mentioned in the blank space left in Clause E and Schedule B manually. You will need to put your initial signature against the clause beforehand and our authorized signatory will manually enter the same and cross sign it.
2. Detailed Annexure-I required. Kindly mail it.
A) The Annexure I mentions the tentative dates of payment schedule for your apartment cost. The same is also reflected on your online portal. If you still require the same separately in mail, kindly let us know. We will send it across to you.
3. CLAUSE
3.2:
I was promised possession of
my flat by Aug 2017 at the time of Booking but as per your clause it
states March 2018 + six months grace time i.e., September 2018 which is more
than a year's delay from what is promised.
Stick to your Original Timelines and Change the
date to Aug 2017 + grace period.
A) The possession of the apartment shall be given starting from December-2017 only. The March-2018 is the completion date in all aspects. The grace period has, therefore, been kept from March-2018.
4. CLAUSE
3.3:
You have already missed your deadline and you
want to compensate it with Rs 3/Sft which is far below market standards. By
completion of your RCC structure I would have paid 92% of my total flat cost
and would be paying Rs. 40,000 towards my EMI and you pay me Rs. 3000 for the
delay caused by you. Even small builders pay Rs 10000 and big builders like
Prestige pay 9% pa of the amount paid. But you want to penalize the purchaser
more than market standards at 16%pa in case of delay in payments. So make it at
par with market standards.
A) This is standard draft approved by our legal team and we will not be able to make any changes in the same.
5. CLAUSE 5.10:
On possession you are liable to get only 4%, in case of delay in taking over how do you justify a penalty of Rs 10000? For an NRI to make travel arrangements in such short notice is difficult.
A) The agreement has been drafted by our legal team
taking care of various aspects and also as per the prevalent real estate market
practices. The draft is standard for all our members and we cannot make any
changes in the same.
You will be given an
advance notice period for completion of sale deed formalities and possession.
If there is a genuine reason for delay from customer’s end, management will
consider the same on case to case basis and provide the grace period as per its
discretion.
6. CLAUSE 7.3:
I was promised complete project altogether which includes club house and
other amenities also, when not completed at time of possession of my flat you
are also liable to pay the penalty like in clause above.
A) We will be handing over the project complete in all aspects by March, 2018. There is a penalty after the grace period as mentioned in the agreement.
7. CLAUSE 9:
Explain Last line - "Developer shall refund the Purchaser, the amounts paid by Purchaser, without any interest, damage or compensation whatsoever after adjusting irrecoverable expenses incurred by Developer" Do you mean to say at times of turmoil only purchaser shall bear ALL the loss?
A) The clause refers to force majeure conditions,
which cannot be predicted. In any case, the developer will always try and
complete the project, as it involves a huge investment from their end also.
8. ANNEXURE-II
Flooring in Living, Bed rooms, Kitchen shall be Vitrified
Tiles only please remove Ceramic Tiles. Vitrified Tiles and Ceramic Tiles are
not equivalent. They are two different materials where in Ceramic Tiles are of
inferior type.
Explain MANUFACTURED
TILES?
A)
We
will not be able to make any changes in the specifications or agreement.
Regarding the manufactured tiles, we will revert on the same soon.
9. ANNEXURE-III
Explain CLAUSE 6.04?
A) The purchaser
shall install air conditioners at the places fixed and approved by developer.