FW: Process for Operating Cost

1 view
Skip to first unread message

Vimala

unread,
Jan 2, 2014, 6:06:43 PM1/2/14
to selvam...@gmail.com, anjappar...@googlegroups.com
FYI
 
I just glimpsed through this email. Not yet checked with numbers what they have put.

 

From: bria...@wilshirebank.com
To: vsh...@hotmail.com; chak...@gmail.com
Subject: FW: Process for Operating Cost
Date: Thu, 2 Jan 2014 22:49:28 +0000

 

 

From: Elizabeth Choe
Sent: Thursday, January 02, 2014 2:19 PM
To: Brian Kang
Subject: RE: Process for Operating Cost

 

Disb.

Date

Payee

Invoice

Business set-up

Working Capital

Soft Costs

TOTAL

ACCUM TOTAL

 

 

 

 

$410,000.00

$14,000.00

$12,000.00

$436,000.00

 

1

10/10/13

NORTHWEST GREEN BUILDERS LLC

CONTRACT

          35,034.03

                         -  

                         -  

 

 

 

"

WILSHIRE STATE BANK

N/A

                         -  

                         -  

          12,000.00

          47,034.03

                        47,034.03

2

10/16/13

V L IMPEX INC

305318

          28,340.05

                         -  

                         -  

          28,340.05

                        75,374.08

3

10/18/13

EAST BAY RESTAURANT SUPPLY INC.

INVOICE

          86,905.83

                         -  

                         -  

 

 

 

"

LIT SIGN MANUFACTURING

9123

             5,890.00

                         -  

                         -  

          92,795.83

                      168,169.91

4

10/25/13

BEST IMAGE FURNISHINGS, INC.

2684

          55,650.00

                         -  

                         -  

          55,650.00

                      223,819.91

5

11/06/13

NORTHWEST GREEN BUILDERS LLC

7013

          70,000.00

                         -  

                         -  

          70,000.00

                      293,819.91

6

11/13/13

NORTHWEST GREEN BUILDERS LLC

7016

          50,000.00

                         -  

                         -  

          50,000.00

                      343,819.91

7

12/06/13

NORTHWEST GREEN BUILDERS LLC

7023

          25,000.00

                         -  

                         -  

          25,000.00

                      368,819.91

8

12/13/13

NORTHWEST GREEN BUILDERS LLC

7024

          15,000.00

                         -  

                         -  

          15,000.00

                      383,819.91

9

12/20/13

NORTHWEST GREEN BUILDERS LLC

7025

          10,000.00

                         -  

                         -  

          10,000.00

                      393,819.91

 

Please be advised that we have final disbursement for Northwest Green in the amount of 18,414.13 and final payment for Lit Signs Manufacturing for 5,890 due. We’ll need a completed site visit prior to the final disbursement and receipt of all approved permits and Certificate of Occupancy.

 

 

Liz Choe

SBA Lending Division

T: 213.427.6587

F: 213.639.8048

 

From: Brian Kang
Sent: Thursday, January 02, 2014 9:36 AM
To: Elizabeth Choe
Subject: FW: Process for Operating Cost

 

Please provide the break down disbursement sheet as of today. With proof of wire information. ( date , to whom,etc)

 

From: Vimala [mailto:vsh...@hotmail.com]
Sent: Thursday, January 02, 2014 7:15 AM
To: Brian Kang
Cc: selvam...@gmail.com; Chakri Mukkasa; Elizabeth Choe
Subject: Process for Operating Cost

 

Brain,

 

It was nice seeing you at our restaurant last week. 

We will be pretty much done with remodeling by end of next week including the kitchen equipment. 

 

As I mentioned during your visit, we have completed required payment disbursements.We are in the verge of opening the restaurant soon.

 

You had mentioned that you will be sending us all invoices and wire transformation details that has been done so far. 

 

Can you please send those details to so as to start the process for operating cash.

 

Vimala Shekar

The information in this email is property of Wilshire Bank. The information transmitted is intended only for the person or entity to which it is addressed and access to this email by anyone else is unauthorized. Any review, re-transmission, dissemination or other use of, or taking of any action or omitted to be taken in reliance upon this information by persons or entities other than the intended recipient is prohibited. If you received this in error, please contact the sender and delete the material from your computer.

Chakri Mukkasa

unread,
Jan 2, 2014, 6:22:58 PM1/2/14
to Vimala, selvam...@gmail.com, anjappar...@googlegroups.com
Can we let Sean know that bank wants to do the final disbursement in the amount of 18,414.13 after the final inspection of the completed site?


--
You received this message because you are subscribed to the Google Groups "Anjappar Seattle" group.
To unsubscribe from this group and stop receiving emails from it, send an email to Anjappar-seatt...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.

Chakri Mukkasa

unread,
Jan 2, 2014, 6:28:01 PM1/2/14
to Vimala, selvam...@gmail.com, anjappar...@googlegroups.com
So, the operating cash will be $17.8K. I guess they will do it after completed site visit...