First thanks to all who despite the terrible weather joined the meeting. This is the spirit which will make us one day one of the best societies of noida extension.
Secondly I would like to thank Mr. Vinod Menon, he took the initiative and noted most of our discussion. He has actually created most of the meeting minutes below and I have just added a few things.
Minutes of the Amrapali Leisure Villa Buyers with Mr. Mohit Gupta -
Place - Amrapali Leisure Valley Site
Date & Time - 3.30 p.m. on 16th February 2013
Mr. Amit Kumar of Amrapali met us and briefly interacted with us and Mr. Mohit Gupta joined at 3.30
p.m. The following issues were discussed with Mr. Mohit Gupta.
1.
Supreme Court Case status: Mr. Mohit Gupta clarified that
Amrapali has given details of how many villas and flats have been sold
already, how many of them are self-financed and how many of them are
bank financed to GNDA, to be shared with the Supreme Court. He felt
confident that the builders who have taken possession of the land, sold
the villas or flats to buyers and already initiated the construction
would not face problems.
2.
Possession Date - Regarding the tentative date for handing over the villas to the
owners, Mr. Mohit Gupta said that the villas will be handed over by
February 2014 as mentioned in the letters sent out by Amrapali, but felt
that there may be a + or – 6 months period involved for all amenities
to be ready. He said that Power back up, water supply, sewerage system,
security and access roads to the villas will be completed by February
2014, though Green Area, Clubs and Community facilities may take some
more time. He assured that at least one Club will be ready by February
2014 and that the front Gate is under construction.
3.
Permission to see the construction - On the question of lifting the instructions denying entry to the
villas by owners, he said that he will need to discuss the same with
the CMD of Amrapali and the Project Director. He assured that he will
revert back to the RWA Representatives within a week as the CMD was away
from New Delhi at present.
4.
Construction Quality: On the complaint about the lack of strict quality control
monitoring, poor quality of bricks and related issues, Mr. Mohit Gupta
informed that the quality of bricks will be improved within a fortnight.
He also said that water proofing component is being used in PCC and
plastering to ensure that there will be no seepage. He has also
designated a Site Engineer Ms. Kiran Budakoti as the focal point
entrusted with the responsibility of liaising with the owners and
sorting out their complaints. Mr. Gupta said that Ms. Kiran will try to
solve problems asap, but also observed that in some cases, she may have
to seek the approval of her seniors and hence we must be prepared for a
week's time for her to address serious issues. Ms. Kiran can be reached
on her cell number
+919716189560 and the complaints can be communicated
to her on her e-mail address
kiran.b...@gmail.com
5.
Cost of the additonal Room - Mr.Mohit Gupta said that on payment of additional 4.9 lakhs,
expandable room on the terrace can be constructed if the same is
required by any owner on his or her villa. This will also have to be
communicated to the site engineer within the coming four to six weeks.
6.
Banking Approvals - Regarding the release of installments by banks, he said that
they are taking it up with the banks to waive the delay for the 18
months due to the situation beyond their control and felt confident that
this will be declared a zero period by most banks as they are fully
aware of the situation.
7.
Actual Villa - Mr. Mohit has said that in around 1 month time a villa will be completed which will have the actual specification mentioned in the BBA, that villa could be treated as the real mock up villa.
8. Mr. Mohit Gupta assured his best cooperation to all the owners
and sought our cooperation in helping them with prompt payment of
installments to ensure that the work is completed at the earliest.
Present:
1. Mr. Sachin Agarwal, B 385, Mobile 8802810191
2. Mr. Sandeep Gupta, A 197, Mobile 9810033750
3. Mr. Varun Chauhan A 111, Mobile 9891400052
4. Mr. Vikas Sangal, A 204, Mobile 9818424018
5. Mr. Saket Goel, A 327, Mobile 9811354583
6. Mr. Rajeev Jain, B 340, Mobile 9910776868
7. Mr. Pardeep Chahal, A 322 Mobile 9711689137
8. Mr. Hari Om Sharma, B 177, Mobile 9654090919
9. Mr. Chandresh Kaushik, B248, Mobile 9811181975
10. Mr. Faiz , A 291, Mobile 9811004852
11. Mr. Sameer Gupta, A 212, Mobile 9630011325
12. Mr. Vinod Menon A 332, Mobile 98210111328
13. Mr. Gaurav Srivastava, Mobile 9810328949
--
Vikas Sangal
Member Consulting Technical Staff
Mentor Graphics