Dear Sally and Rusnitah,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works along Park Street, specifically between Lamp Post 16F and 26F. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
The submission includes a site plan (to scale) and a layout plan clearly indicating the proposed works in relation to the RTS first reserve. Additionally, we have provided detailed plan and cross-section drawings (to scale) showing trench dimensions and excavation depths. The method statement outlines the proposed construction methodology and incorporates comprehensive safety control measures to mitigate any risk of damage to existing RTS structures and associated facilities.
Furthermore, we have enclosed valid machine test certificates and operator certifications, as well as a toppling analysis and machine clearance assessment in relation to MRT/LRT viaduct structures, where applicable.
We appreciate your assistance in reviewing this submission and look forward to your approval to proceed with the proposed works. Please do not hesitate to contact us should you require any clarification or further information.
Thanks and Regards,
Francis Edward I. Angad
Project Engineer
Or Kim Peow Contractors (Pte) Ltd
Dear Yang,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works along Kim Seng Rd, specifically between Lamp Post 10F and 1. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
Dear Yang,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works along River Valley Rd, specifically between Lamp Post 31F and LP 85/2F. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
The submission includes a site plan (to scale) and a layout plan clearly indicating the proposed works in relation to the RTS first reserve. Additionally, we have provided detailed plan and cross-section drawings (to scale) showing trench dimensions and excavation depths. The method statement outlines the proposed construction methodology and incorporates comprehensive safety control measures to mitigate any risk of damage to existing RTS structures and associated facilities.
Furthermore, we have enclosed valid machine test certificates and operator certifications, as well as a toppling analysis and machine clearance assessment in relation to MRT/LRT viaduct structures, where applicable.
We appreciate your assistance in reviewing this submission and look forward to your approval to proceed with the proposed works. Please do not hesitate to contact us should you require any clarification or further information.
Thanks and Regards,
Francis Edward I. Angad
Senior Project Engineer
Dear Yang and Tan,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works at Scotts Rd LP 68 to LP 62; Clemenceau Ave N LP 22F to LP 24; Bukit Timah Rd LP 65 to LP 61. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
The submission includes a site plan (to scale) and a layout plan clearly indicating the proposed works in relation to the RTS first reserve. Additionally, we have provided detailed plan and cross-section drawings (to scale) showing trench dimensions and excavation depths. The method statement outlines the proposed construction methodology and incorporates comprehensive safety control measures to mitigate any risk of damage to existing RTS structures and associated facilities.
Furthermore, we have enclosed valid machine test certificates and operator certifications, as well as a toppling analysis and machine clearance assessment in relation to MRT/LRT viaduct structures, where applicable.
We appreciate your assistance in reviewing this submission and look forward to your approval to proceed with the proposed works.
Thanks and Regards,
Dear Sir,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works at South Bridge Rd LP 7 to LP 3; Maxwell Rd LP 1/1F to LP 2; Tanjong Pagar Rd LP 1 to LP 2. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
Morning Francis,
You may liaise directly with Ei Ei, who is copied in this email, regarding your request.
Aside to Ei Ei,
I understand that Tiam Yong is on leave. Refer below for your necessary action.
Thank you and best regards,
|
|
Mohd Amin | Deputy Manager, Development & Building Control (Rail), Infrastructure Design & Engineering Group |
|
|
|
251 North Bridge Road, Singapore 179102 |
|
WARNING: "Privileged/Confidential information may be contained in this message. If you are not the intended addressee, you must not copy, distribute or take any action in reliance thereon.
Communication of any information in this email to any unauthorized person is an offence under the Official Secrets Act (Cap 213). Please notify the sender immediately if you receive this in error."
From: Francis Edward Iglesia Angad <franci...@okph.com>
Sent: Thursday, 4 December 2025 7:01 pm
To: Mohamad Amin ABDUL RASHID (LTA) <Mohamad_Amin...@lta.gov.sg>
Cc: LTA-DBC Registry (LTA) <LTA-DBC_...@lta.gov.sg>; Shiela ANG (LTA) <Shiel...@lta.gov.sg>; Zufri WAHAB (LTA) <Zufri...@lta.gov.sg>; Chua Hock Beng <chuahock...@yahoo.com.sg>; am20...@googlegroups.com; nearyclev...@gmail.com;
khee...@gmail.com; Kance Liong <kance...@okph.com>; Gui GeYi <gui...@okph.com>; Vinci Ma Huai En <vin...@okph.com>; Cordelia Herbert <cord...@okph.com>; Vellaiyan Balamahendra Muniappa <vell...@okph.com>; Levie Vallente <vallen...@okph.com>; Gian
Karlo Antalan <ant...@okph.com>; Than Than Soe <thant...@okph.com>; Yi Shien NG (LTA) <NG_Yi...@lta.gov.sg>
Subject: RE: AM201 - DBC Approval Request for works at South Bridge Rd LP 7 to LP 3; Maxwell Rd LP 1/1F to LP 2; Tanjong Pagar Rd LP 1 to LP 2
|
[WARNING: EXTERNAL EMAIL] Exercise caution before opening attachments, clicking links or sharing information. |
Dear Yang,
We are writing to seek your kind attention and approval for the DBC submission pertaining to the proposed works at Tiong Bahru Rd between LP 24 to LP 27. In line with LTA’s requirements, we have attached the duly completed DBC Rail S1 Form along with the relevant supporting documents for your review.
The submission includes a site plan (to scale) and a layout plan clearly indicating the proposed works in relation to the RTS first reserve. Additionally, we have provided detailed plan and cross-section drawings (to scale) showing trench dimensions and excavation depths. The method statement outlines the proposed construction methodology and incorporates comprehensive safety control measures to mitigate any risk of damage to existing RTS structures and associated facilities.
Furthermore, we have enclosed valid machine test certificates and operator certifications, as well as a toppling analysis and machine clearance assessment in relation to MRT/LRT viaduct structures, where applicable.
We appreciate your assistance in reviewing this submission and look forward to your approval to proceed with the proposed works.
Thanks and Regards,
Dear Francis Edward I. Angad,
Please clarify whether URA WP/PP is required for the proposed construction of cycling path.
Thank you and best regards,
Mohd Amin | Deputy Manager, Development & Building Control (Rail), Infrastructure Design & Engineering Group
|
|
1 Hampshire Road Singapore 219428 |
WARNING: "Privileged/Confidential information may be contained in this message. If you are not the intended addressee, you must not copy, distribute or take any action in reliance thereon.
Communication of any information in this email to any unauthorized person is an offence under the Official Secrets Act (Cap 213). Please notify the sender immediately if you receive this in error."
From: Francis Edward Iglesia Angad <franci...@okph.com>
Sent: Thursday, 19 March 2026 4:50 pm
To: Mohamad Amin ABDUL RASHID (LTA) <Mohamad_Amin...@lta.gov.sg>
Cc: LTA-DBC Registry (LTA) <LTA-DBC_...@lta.gov.sg>; Shiela ANG (LTA) <Shiel...@lta.gov.sg>; Zufri WAHAB (LTA) <Zufri...@lta.gov.sg>; Chua Hock Beng <chuahock...@yahoo.com.sg>; am20...@googlegroups.com; nearyclev...@gmail.com;
khee...@gmail.com; Kance Liong <kance...@okph.com>; Gui GeYi <gui...@okph.com>; Vinci Ma Huai En <vin...@okph.com>; Cordelia Herbert <cord...@okph.com>; Vellaiyan Balamahendra Muniappa <vell...@okph.com>; Levie Vallente <vallen...@okph.com>; Gian
Karlo Antalan <ant...@okph.com>; Than Than Soe <thant...@okph.com>; Yi Shien NG (LTA) <NG_Yi...@lta.gov.sg>
Subject: RE: AM201 - DBC Approval Request for works at South Bridge Rd LP 7 to LP 3; Maxwell Rd LP 1/1F to LP 2; Tanjong Pagar Rd LP 1 to LP 2
|
[WARNING: EXTERNAL EMAIL] Exercise caution before opening attachments, clicking links or sharing information. |
Dear Sir,
Hi sir,
Please see attached URA PP Exemption correspondence as shared by our client’s consultant previously.
Thanks and Regards,
Francis Edward I. Angad
Or Kim Peow Contractors (Pte) Ltd