As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. 


Residential/Hotel 


  • There will be work this Saturday, December 23rd starting at 7AM. 

                       Crews will be installing forms and rebar inside the foundation area. 

                       Tower cranes will be operational. 

  • Concrete operations are ongoing. 

                       Multiple placements are scheduled to take place over the next two weeks. 

                                     These placements will start during normal work hours. 

                                     Finishing work may continue past normal operation hours. 

  • Waterproofing work continues on the site foundation. 

  • A large generator is operating to provide temporary power to the site. 

                       This generator will run 24/7 to support the power needs, especially heaters, on the site. 

  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. 


Laboratory and Office Buildings 


  • Concrete and rebar operations are ongoing. 

  • Waterproofing work continues on the site foundation. 

  • Formwork and raker post activities will continue. 


Greenway 


  • This section of the site is currently being used for laydown space. 


Treehouse Conference Center 


  • There will be work this Saturday, December 23rd starting at 7AM. 

                      Crews will be installing formwork and waterproofing inside the foundation area. 

  • Installing rebar, formwork and waterproofing will continue. 

  • Concrete operations are ongoing. 


Building Mock-Ups 


  • Crews continue to work at the Laboratory and Hotel mockups. 

  • Work will continue at the Residential and Treehouse Conference Center mockups. 

  • A crane and truck will periodically be in the lane on Rotterdam Street adjacent to the mockup lot site. 


CONTACT US 


If you have any questions or concerns, please email us at constr...@ercallston.com or call us at (617) 892-8972

Anthony D'Isidoro

unread,
Jan 6, 2024, 9:17:59 AMJan 6
to Anthony D'Isidoro
Enterprise Research Campus Update #22 (Week of January 8, 2024) 

January 5, 2024 


After hours snow removal work will take place through the winter months as inclement weather events occur.  


As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. 


Residential/Hotel 


  • There will be work this Saturday, January 6th starting at 7AM.  

                       Crews will be placing concrete and preparing for the winter storm. 

                       Tower cranes will be operational. 

  • Concrete operations are ongoing. Intermittent use of power trowels for concrete finishing will take place after 6PM. 

  • Crews continue erecting the hotel core structure. 

  • A large generator is operating to provide temporary power to the site. 

                       This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of temporary                           power is complete. 

  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. 


Laboratory and Office Buildings 


  • A crew will be preparing for the winter storm this Saturday, January 6th starting at 7AM. 

  • Concrete and rebar operations are ongoing. 

                       Crews are working on wall placements with two to three placements a week. 

  • Excavation of the site’s east berm will continue for the next two weeks. 

  • Waterproofing work continues on the site foundation. 


Greenway 


  • This section of the site is currently being used for laydown space. 


Treehouse Conference Center 


  • There will be work this Saturday, January 6th starting at 7AM. 

                       Crews will be installing plumbing and electric  l within the foundation area. 

  • Work continues on the spread footings and waterproofing. 

  • Concrete and rebar operations are ongoing. 


Building Mock-Ups 


  • Concrete and drywall work will take place at the Residential/Hotel mockups. 

  • Mass Timber delivery is expected at the Treehouse Conference Center mockup. 

  • Punchlist work is ongoing at the Laboratory mockup. 

 

Anthony D'Isidoro

unread,
Jan 12, 2024, 7:37:38 PMJan 12
to Anthony D'Isidoro
Enterprise Research Campus Update #23 (Week of January 15, 2024) 

January 12, 2024 


All sites will have crews working on Monday, January 15th. 


As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. 


Residential/Hotel 


  • There will be work this Saturday, January 13th starting at 7AM. 

                           Preparation for concrete placements will be underway. 

                           Tower cranes will be operational. 

  • Concrete operations are ongoing. Intermittent use of power trowels for concrete finishing will take place after 6PM. 

  • Crews continue erecting the hotel core structure. 

  • More visible work is taking place on the sky deck and level two. 

  • A large generator is operating to provide temporary power to the site. 

                            This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of                                                 temporary power is complete. 

  • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. 


Laboratory and Office Buildings 


  • There will be no work on site this Saturday. 

  • Concrete and rebar operations are ongoing. 

                            Crews are working on wall placements with two to three placements a week. 

  • Excavation of the site’s east berm will continue. 


Greenway 


  • This section of the site is currently being used for laydown space. 


Treehouse Conference Center 


  • There will be work this Saturday, January 13th starting at 7AM. 

                            Iron workers, electricians, and plumbers will be working within the site foundation. 

  • A 300-yard slab placement is scheduled for Friday, January 19th. Concrete finishers with power trowels will be on site. 

  • Concrete and rebar operations are ongoing. 


    Building Mock-Ups 


    • Sheeting work will take place at the Residential/Hotel mockups. 

    • Mass Timber delivery is expected at the Treehouse Conference Center mockup. 

    • Punchlist work is ongoing at the Laboratory mockup. 

    Anthony D'Isidoro

    unread,
    Jan 20, 2024, 6:46:06 PMJan 20
    to Anthony D'Isidoro
    Enterprise Research Campus Update #24 (Week of January 22, 2024) 

    January 19, 2024 


    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. 


    Residential/Hotel 


    • There will be work this Saturday, January 20th starting at 7AM. 

                        Preparation for concrete placements will be underway. 

                        Crews will be working on the high-rise core. 

                        Tower cranes will be operational. 

    • Concrete operations are ongoing. Intermittent use of power trowels for concrete finishing will take place after 6PM. 

    • Crews continue erecting the hotel core structure. 

    • More visible work is taking place on the sky deck and level two. 

    • A large generator is operating to provide temporary power to the site. 

                        This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of temporary                            power is complete. 

    • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. 


    Laboratory and Office Buildings 


    • There will be no work on site this Saturday. 

    • Concrete and rebar operations are ongoing. 

                         Crews are working on wall placements with two to three placements a week. 


    Greenway 


    • This section of the site is currently being used for laydown space. 


    Treehouse Conference Center 


    • There will be work this Saturday, January 20th starting at 7AM. 

                         Crews will be working within the site foundation. 

    • Concrete and rebar operations are ongoing. 


    Building Mock-Ups 


    • Structure and sheeting work will take place at the Residential/Hotel mockups. 

    • Mass Timber delivery is expected at the Treehouse Conference Center mockup. 

    • Punchlist work is ongoing at the Laboratory mockup.  

    Anthony D'Isidoro

    unread,
    Jan 27, 2024, 9:05:17 AMJan 27
    to Anthony D'Isidoro
    Enterprise Research Campus Update #25 (Week of January 29, 2024) 

    January 26, 2024 


    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


    Residential/Hotel


    • There will be work this Saturday, January 27th starting at 7AM.

                         Crews will be preparing for concrete placements and working on the high-rise core.

                         Tower cranes will be operational.

    • Concrete operations are ongoing. Intermittent use of power trowels for concrete finishing will take place after 6PM.

    • Crews continue erecting the hotel core structure.

    • Visible work is taking place on the sky deck and level two.

    • A large generator is operating to provide temporary power to the site.

                          This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of temporary                            power is complete.

    • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


    Laboratory and Office Buildings


    • There will be a crew on site working on dewatering this Saturday.

    • Concrete and rebar operations are ongoing.

                          Crews are working on wall placements with two to three placements a week.

    • Crews are preparing for their next mat slab placement on
      Monday, February 5th.

                           A 5AM start will be needed for this operation.


    Greenway


    • This section of the site is currently being used for laydown space.


    Treehouse Conference Center


    • There will be work this Saturday, January 27th starting at 7AM.

                            Crews will be working on foundation formwork.

    • Concrete and rebar operations are ongoing.


    Building Mock-Ups


    • Work will take place at the Residential/Hotel mockups.

    • Treehouse Conference Center mockup is awaiting Mass Timber delivery.

    • Punchlist work is ongoing at the Laboratory mockup.

    Anthony D'Isidoro

    unread,
    Feb 7, 2024, 10:36:04 PMFeb 7
    to Anthony D'Isidoro
    Enterprise Research Campus Update #26 (Week of February 5, 2024) 

    February 7, 2024 


    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


    Residential/Hotel


    • There will be work this Saturday, February 3rd, starting at 7AM.

                             Crews will be preparing for concrete placements and working on the high-rise core.

                             Tower cranes will be operational.

                             An electrical switchover from generator to temporary power is planned, which may continue on Sunday, February 4th.

    • Concrete operations are ongoing. A slab placement is planned for Tuesday, February 6th. Intermittent use of power trowels for concrete finishing will take place after 6PM.

    • Crews continue erecting the hotel core structure.

    • Visible work is taking place on the sky deck and level two.

    • A large generator is operating to provide temporary power to the site.

                             This generator will run 24/7 to support the power needs, especially heaters, on the site until installation of temporary                             power is complete.

    • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


    Laboratory and Office Buildings


    • There will be no work this Saturday.

                             Some crews will be on site Sunday to turn on heaters in preparation for Monday’s concrete placement.

    • Concrete and rebar operations are ongoing.

                             Crews are working on wall placements with two to three placements a week.

    • A mat slab placement is scheduled for Monday, February 5th.

                             A 5AM start will be needed for this operation.

    • Crews are preparing for the first of two tower cranes to be erected towards the end of February.


    Greenway


    • This section of the site is currently being used for laydown space.


    Treehouse Conference Center


    • There will be work this Saturday, February 3rd, starting at 7AM.

                             Crews will be working on basement walls rebar and formwork.

    • Concrete and rebar operations are ongoing.


    Building Mock-Ups


    • Work will take place at the Residential/Hotel mockups.

    • Treehouse Conference Center mockup is awaiting Mass Timber delivery.

    • Punchlist work is ongoing at the Laboratory mockup.


    General


    • Drones will be in use weekly to monitor construction progress on site.

                             Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                             Flights are weather dependent and are scheduled on Wednesdays and Thursdays from 7AM to 9AM alternating weekly.

                             A drone flight is scheduled on Wednesday, February 7th from 7AM to 9AM. 

    Anthony D'Isidoro

    unread,
    Feb 9, 2024, 3:40:35 PMFeb 9
    to Anthony D'Isidoro
    Enterprise Research Campus Update #27 (Week of February 12, 2024) 

    February 9, 2024 


    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


    Residential/Hotel


    • There will be work this Saturday, February 10th, starting at 7AM.

                             Crews will be preparing for concrete placements.

                             Tower cranes will be operational.

    • Concrete operations are ongoing.

    • Intermittent use of power trowels for concrete finishing may take place after 6PM.

    • Crews continue erecting the hotel core structure.

    • Visible work is taking place on the sky deck and level two.

    • Temporary power has been installed on site.

                             The large generators needed to support the site’s power needs have been removed.

    • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


    Laboratory and Office Buildings


    • There will be work this Saturday, February 10th, starting at 7AM.

                              Crews will be removing bracing inside the foundation.

    • Concrete and rebar operations are ongoing.

                               Crews are working on wall placements with two to three placements a week.

    • Crews are preparing for the first of two tower cranes to be erected on February 24th and 25th.

                               An early start and after-hours work may be needed to support this operation.

    • Temporary power is being installed on site.


    Greenway


    • This section of the site is currently being used for laydown space.


    Treehouse Conference Center


    • There will be work this Saturday, February 10th, starting at 7AM.

                                Concrete crews will be working on the walls and core.

    • Concrete placements and rebar operations are ongoing.

    • Temporary power is being installed on site.


    Building Mock-Ups


      • Work will take place at the Residential/Hotel mockups.

      • Treehouse Conference Center mockup is awaiting Mass Timber delivery.

      • Punchlist work is ongoing at the Laboratory mockup.

      • Intermittent deliveries may take place on Rotterdam Street.


      General


      • Drones will be in use weekly to monitor construction progress on site.

                                  Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                  Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7AM to 9AM alternating weekly.

                                  No drone flights are scheduled next week.

      • After hours snow removal operations will be ongoing throughout the winter months during periods of inclement weather.

      Anthony D'Isidoro

      unread,
      Feb 16, 2024, 4:47:10 PMFeb 16
      to Anthony D'Isidoro
      Enterprise Research Campus Update #28 (Week of February 19, 2024) 

      February 16, 2024 


      As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


      All sites will not be working on the holiday, Monday, February 19th.


      Residential/Hotel


      • There will be work this Saturday, February 17th, starting at 7AM.

                           Crews will be preparing for concrete placements.

                           Tower cranes will be operational.

      • Concrete operations are ongoing.

      • Intermittent use of power trowels for concrete finishing may take place after 6PM.

      • Crews continue erecting the hotel core structure.

      • Visible work is taking place on the sky deck and level two.

      • Temporary overhead power will be installed on site to power the field trailers and eliminate remaining generators on site.

      • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


        Laboratory and Office Buildings


        • There will be work this Saturday, February 17th, starting at 7AM.

                              Crews will be placing crushed stone on the foundation bottom.  No trucking in or out.

          • Concrete and rebar operations are ongoing.

          • Continue to place crushed stone on the foundation bottom.

          • Crews are preparing for the first of two tower cranes to be erected on Saturday, February 24th and Sunday, February 25th.

                                 A 6AM start and possible after-hours work will be needed to support this operation.

          • Temporary power is being installed on site


          Greenway


          • This section of the site is currently being used for laydown space.


          Treehouse Conference Center


          • There will be work this Saturday, February 17th, starting at 7AM.

                                  Concrete crews will be preparing for wall placements.

          • Concrete placements and rebar operations are ongoing.

          • Temporary power is being installed on site.


          Building Mock-Ups


          • Work will take place at the Residential/Hotel mockups.

          • Treehouse Conference Center mockup is awaiting Mass Timber delivery.

          • Punchlist work is ongoing at the Laboratory mockup.

          • A lane shift around lifts and Intermittent deliveries will take place on Rotterdam Street.


          General


          • Drones will be in use weekly to monitor construction progress on site.

                                  Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                  Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7AM to 9AM alternating weekly.

                                  No drone flights are scheduled next week.

                                  A drone flight will take place on Thursday, February 22nd from 7AM to 9AM.

          Anthony D'Isidoro

          unread,
          Feb 23, 2024, 5:00:06 PMFeb 23
          to Anthony D'Isidoro
          Enterprise Research Campus Update #29 (Week of February 26, 2024) 

          February 23, 2024 


          As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


          Residential/Hotel


          • There will be work this Saturday, February 24th, starting at 7AM.

                             Crews will be preparing for concrete placements.

                             Tower cranes will be operational.

          • Concrete operations are ongoing.

          • Intermittent use of power trowels for concrete finishing may take place after 6PM.

          • Crews continue erecting the hotel core structure.

          • Visible work is taking place on the sky deck and level two.

          • Temporary overhead power will be installed on site to power the field trailers and eliminate another generator on site.

          • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


            Laboratory and Office Buildings


            • There will be work this Saturday, February 24th, starting at 7AM.

                               Crews will be removing bracing.

              • Concrete and rebar operations are ongoing.

              • Continue to place crushed stone on the foundation bottom.

              • Crews are preparing for the first of two tower cranes to be erected on Saturday, March 2nd and Sunday, March 3rd.

                                 A 6AM start and possible after-hours work will be needed to support this operation.

              • Temporary power is being installed on site.


              Greenway


              • This section of the site is currently being used for laydown space.


              Treehouse Conference Center


              • There will be work this Saturday, February 24th, starting at 7AM.

                                 Concrete crews will be preparing for wall placements.

              • Concrete placements and rebar operations are ongoing.

              • Temporary power is being installed on site.


              Building Mock-Ups


              • Work will take place at the Residential/Hotel mockups.

              • Treehouse Conference Center mockup mass timber panels are being installed and other work continues.

              • Punchlist work is ongoing at the Laboratory mockup.

              • A lane shift around lifts and intermittent deliveries will take place on Rotterdam Street.


              General


              • Drones will be in use bi-weekly to monitor construction progress on site.

                                 Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                 Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7AM to 9AM alternating weekly.

                                 No drone flights are scheduled next week.

              • After hours snow removal operations will be ongoing throughout the winter months during periods of inclement weather.

              Anthony D'Isidoro

              unread,
              Mar 1, 2024, 9:29:40 PMMar 1
              to Anthony D'Isidoro
              Enterprise Research Campus Update #30 (Week of March 4, 2024) 

              March 1, 2024 


              As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


              Residential/Hotel


              • There will be work this Saturday, March 2nd starting at 7AM.

                                 Crews will be preparing for concrete placements.

                                 Tower cranes will be operational.

              • Concrete operations are ongoing.

              • Intermittent use of power trowels for concrete finishing may take place after 6PM.

              • Crews continue erecting the hotel core structure.

              • Visible work is taking place on the sky deck, level two and beginning on level three.

              • Temporary overhead electrical connection has been installed on site to power the field trailers and has eliminated another large generator on site.

              • The site’s two tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.


                Laboratory and Office Buildings


                • Crews will be assembling and installing the first of two tower cranes beginning on Friday, March 1st.  On Saturday, March 2nd, starting at 6AM, installation of the crane will continue. If needed, work may take place on Sunday, March 3rd.

                • Sixteen truckloads of crane sections will mostly be delivered to the site on Friday.

                                   Possible after-hours work will be needed to support this operation.

                • Steel will begin to be delivered and installed starting on Monday, March 4th.

                • Concrete and rebar operations are ongoing.

                • Temporary power is being installed on site.


                Greenway


                • This section of the site is currently being used for laydown space.


                Treehouse Conference Center


                • There will be work this Saturday, March 2nd, starting at 7AM.

                                   Concrete crews will be preparing for wall placements.

                • Work is underway on the elevator core.

                • Concrete placements and rebar operations are ongoing.

                • Temporary power is being installed on site.


                  Building Mock-Ups


                    • Work will take place at the Residential/Hotel mockups.

                    • Treehouse Conference Center mockup work continues.

                    • Punchlist work is ongoing at the Laboratory mockup.

                    General


                    • Drones will be in use bi-weekly to monitor construction progress on site.

                                       Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                       Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7AM to 9AM alternating weekly.

                                       A drone flight is scheduled for Wednesday, March 6th from 7AM to 9AM.

                    Anthony D'Isidoro

                    unread,
                    Mar 16, 2024, 9:26:51 AMMar 16
                    to Anthony D'Isidoro
                    Enterprise Research Campus Update #32 (Week of March 18, 2024) 

                    March 15, 2024 


                    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                    Residential/Hotel

                    • There will be work this Saturday, March 16 starting at 7 a.m.  

                                     Crews will be preparing for concrete placements.  

                                     Tower cranes will be operational. 

                    • Concrete operations are ongoing. 

                    • Intermittent use of power trowels for concrete finishing may take place after 6 a.m. 

                    • Crews continue erecting the hotel core structure.  

                    • Visible work is underway on the sky deck, level two and level three.   

                    Laboratory and Office Buildings

                    • Structural steel continues to be delivered and installed on the first floor of the west tower using the tower crane.  

                    • Under-slab plumbing/piping continues installation followed by placing drainage stone on the east building. 

                    Greenway

                    • This section of the site is currently being used for laydown space.

                    Treehouse Conference Center

                    • Work will take place this Saturday, March 16, starting at 7 a.m.  

                                     Concrete crews will be preparing for placements.  

                      • Work is underway on the elevator core. 

                      • Concrete placements and rebar operations are ongoing.  

                      • Temporary power is being installed on site.  Eversource may use a vacuum truck.   

                      Building Mock-Ups

                      • Punchlist work is ongoing on all five mockups.  

                      General

                      • The site’s three tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind. 

                                       Drones will be in use bi-weekly to monitor construction progress on site. 

                                       Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations. 

                                       Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7 a.m. to 9 a.m. alternating weekly. 

                                       A drone flight is scheduled for Thursday, March 21 from 7 a.m. to 9 a.m.

                      Anthony D'Isidoro

                      unread,
                      Mar 25, 2024, 4:28:10 PMMar 25
                      to Anthony D'Isidoro
                      Enterprise Research Campus Update #33 (Week of March 25, 2024) 

                      March 21, 2024 


                      As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                      Residential/Hotel

                      • Work will be underway this Saturday, March 23 starting at 7 a.m.

                                            Crews will be preparing for concrete placements.

                                            Core equipment removal will be taking place.

                                            Tower cranes will be operational.

                      • Concrete operations are ongoing.

                      • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                      • The hotel core is complete.

                      • Visible work is underway on level three of the high rise and midrise residential buildings.

                      Laboratory and Office Buildings

                      • Structural steel continues to be delivered and installed and rising to the second level on the of the west tower using the tower crane.

                      • Drainage stone will be placed on the east building.

                      Greenway

                      • This section of the site is currently being used for laydown space.

                      Treehouse Conference Center

                      • Work will take place this Saturday, March 23, starting at 7 a.m.

                                            Concrete crews will be preparing for placements.

                      • Work is underway on the elevator core.

                      • Backfilling is underway.

                      • Concrete placements are ongoing.

                      • Temporary power is being installed on site.  Eversource may use a vacuum truck.

                      Building Mock-Ups

                      • Punchlist work is ongoing on all five mockups.  

                      General

                      • The site’s three tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                      • Drones will be in use bi-weekly to monitor construction progress on site.

                                            Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                            Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7 a.m. to 9 a.m. alternating weekly.

                                            A drone flight is scheduled for Friday, March 22 from 10 a.m. to noon.

                      • After hours snow removal operations will be ongoing during periods of inclement weather.

                      Anthony D'Isidoro

                      unread,
                      Mar 30, 2024, 11:57:13 AMMar 30
                      to Anthony D'Isidoro
                      Enterprise Research Campus Update #34 (Week of April 1, 2024) 

                      March 29, 2024 


                      As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                      Residential/Hotel

                      • Work will be underway this Saturday, March 30 starting at 7 a.m.

                                       Crews will be preparing for concrete placements and steel erection.

                                       Core equipment removal will be taking place.

                                       Tower cranes will be operational.

                      • Concrete operations are ongoing.

                      • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                      • The hotel core is complete.

                      • Steel preparation is ongoing at the hotel.

                      • Visible work is underway on level four and five of the high rise and midrise residential buildings.

                      Laboratory and Office Buildings

                      • Structural steel continues to be delivered and installed and rising to the third level on the of the west tower using the tower crane.

                      • Crews are preparing to install a tower crane the week of April 8 for structural steel installation on the east building.

                      Greenway

                      • This section of the site is currently being used for laydown space.

                      Treehouse Conference Center

                      • Work will take place this Saturday, March 30, starting at 7 a.m.

                                       Crews will be preparing for placements.

                                       Masons will be working on the core.

                        • Work is underway on the elevator core.

                        • Drainage structures are being installed.

                        • Smaller concrete placements are ongoing.

                        • Temporary power is being installed on site.  Eversource may use a vacuum truck.

                        Building Mock-Ups

                        • Punchlist work is ongoing on all five mockups.  

                        General

                        • The site’s three tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                                         Drones will be in use bi-weekly to monitor construction progress on site. 

                                         Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                         Flights are weather dependent and are scheduled Wednesdays or Thursdays from 7 a.m. to 9 a.m. alternating weekly.

                                         A drone flight is scheduled for Friday, April 5 from 7 a.m. to 9 a.m.

                        Anthony D'Isidoro

                        unread,
                        Apr 6, 2024, 9:33:07 AMApr 6
                        to Anthony D'Isidoro
                        Enterprise Research Campus Update #35 (Week of April 8, 2024) 

                        April 5, 2024 


                        As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                        Residential/Hotel

                        • Work will be underway this Saturday, April 6 starting at 7 a.m.

                                             Crews will be preparing for concrete placements and steel erection.

                                             Tower cranes will be operational.

                        • Structural steel will be delivered and begin to be installed at the hotel on Monday, April 8.

                        • Concrete operations are ongoing.

                        • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                        • Visible work is underway on level four and five of the high rise and midrise residential buildings.

                        Laboratory and Office Buildings

                        • A tower crane will be assembled beginning on Monday, April 8 for structural steel installation to start the week of April 16 on the east building.

                        • The large crawler crane will be disassembled and removed on Thursday, April 11 and Friday, April 12.

                        • Next week some off-hours work will be required to assemble and disassemble the cranes from 6 a.m. to 8 p.m. An early-hour, wide-load equipment pick up may be necessary.

                        • Structural steel continues to be delivered and installed and rising to the third level on the of the west tower using the tower crane.

                          Greenway

                          • This section of the site is currently being used for laydown space.

                          Treehouse Conference Center

                          • Work will take place this Saturday, April 6, starting at 7 a.m.

                                               Crews will be preparing for placements.

                                               Masons will be working on the core.

                                               Rigging will be installed.

                          • Work is underway on the elevator cores with concrete placements scheduled to begin weekly on April 10.

                          • Smaller concrete placements are ongoing.

                          • Temporary power is being installed on site. Eversource may use a vacuum truck.

                          Building Mock-Ups

                          • Punchlist work is ongoing on all five mockups.  

                          General

                          • The site’s three tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                          • Drones will be in use bi-weekly to monitor construction progress on site.

                                               Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                               Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                           weekly.

                          Anthony D'Isidoro

                          unread,
                          Apr 14, 2024, 5:49:47 PMApr 14
                          to Anthony D'Isidoro
                          Enterprise Research Campus Update #36 (Week of April 15, 2024) 

                          April 12, 2024 


                          All sites will not be working on the Patriots Day holiday on Monday, April 15, 2024.  


                          As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                          Residential/Hotel

                          • Work will be underway this Saturday, April 13 starting at 7 a.m.

                                             Structural steel will be installed at the hotel.

                                             Crews will be preparing for concrete placements and steel erection.

                                             Tower cranes will be operational.

                          • Structural steel continues to be delivered and installed at the hotel.

                          • Concrete operations are ongoing.

                          • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                          • Visible work is underway with work progressing to level six of the high rise and midrise residential buildings.

                          Laboratory and Office Buildings

                          • A second tower crane has been assembled and will be operating to begin installing structural steel on the east building.

                          • The large crawler crane has been removed.

                          • Structural steel continues to be delivered and installed and rising to the fourth level on the of the west tower using the tower crane.

                          • Structural steel deliveries continue.

                          Greenway

                          • This section of the site is currently being used for laydown space.

                          Treehouse Conference Center

                          • Work will take place this Saturday, April 13, starting at 7 a.m.

                                            Crews will be preparing for placements.

                                            Masons will be working on the core.

                                            Rigging will be installed.

                                            A crane will be operating on site.

                          • Work is underway on the elevator cores with concrete wall placements scheduled to begin on Tuesday, April 16 and continuing one placement a week through the month.

                          • Underground utility work is taking place inside the site.

                          • Temporary power is being installed on site.  Eversource may use a vacuum truck off Western Avenue.

                          Building Mock-Ups

                          • Punchlist work is ongoing on all five mockups.  

                          General

                          • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                          • Drones will be in use bi-weekly to monitor construction progress on site.

                                            Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                            Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                            weekly.

                                            A drone flight is scheduled for Thursday, April 18 from 9 a.m. to 10 a.m. or Friday, April 19 from 7 a.m. to 9 a.m.

                          Anthony D'Isidoro

                          unread,
                          Apr 20, 2024, 9:14:40 AMApr 20
                          to Anthony D'Isidoro
                          Enterprise Research Campus Update #37 (Week of April 22, 2024) 

                          April 19, 2024 


                          As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                          Residential/Hotel

                          • Work will be underway this Saturday, April 20 starting at 7 a.m.

                                         Utility exploratory test pits will be conducted at the middle gate at Western Avenue and inside the fence.

                                         Crews will be preparing for concrete placements and steel erection.

                                         Tower cranes will be operational.

                          • Structural steel continues to be delivered and installed at the hotel.  Crews working on level five.

                          • Concrete operations are ongoing.

                          • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                          • Visible work is underway with work progressing to level six of the high rise and midrise residential buildings.

                            Laboratory and Office Buildings

                            • Work will be underway this Saturday, April 20 starting at 7 a.m.

                                           A small crew will be doing steel work and clean up.

                            • The two tower cranes are operating and structural steel continues to be delivered and installed on both the east and west buildings.

                            Greenway

                            • This section of the site is currently being used for laydown space.

                            Treehouse Conference Center

                            • Work will take place this Saturday, April 20, starting at 7 a.m.

                                           Crews will be preparing for placements.

                                           Masons will be working on the core.

                                           A crane will be operating on site.

                            • Work is underway on the elevator cores with a concrete placement early next week.

                            • Underground utility work is taking place inside the site.

                            • Temporary power is being installed on site. Eversource may use a vacuum truck on Friday, April 19 or on Monday, April 22 off Western Avenue.

                            Building Mock-Ups

                            • Punchlist work is ongoing on all five mockups.  

                            General

                            • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                            • Drones will be in use bi-weekly to monitor construction progress on site.

                                           Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                           Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                           weekly.

                                           A drone flight is scheduled for Friday, April 19 from 7 a.m. to 9 a.m.

                            Anthony D'Isidoro

                            unread,
                            Apr 28, 2024, 9:21:15 AMApr 28
                            to Anthony D'Isidoro
                            Enterprise Research Campus Update #38 (Week of April 29, 2024) 

                            April 26, 2024 


                            As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                            Residential/Hotel

                            • Work will be underway this Saturday, April 27 starting at 7 a.m.  

                                                Utility tie-ins will be underway inside the site on Trotting Avenue. 

                                                Crews will be preparing for concrete placements and steel erection. 

                                                Tower cranes will be operational. 

                            • Structural steel continues to be delivered and installed at the hotel, rising up to level seven. 

                            • Concrete operations are ongoing. 

                            • Utility tie-ins continue inside the site on Trotting Avenue. 

                            • Intermittent use of power trowels for concrete finishing may take place after 6 a.m. 

                            • Visible work is underway with work progressing to level six and seven of the high rise and midrise residential buildings.   

                            Laboratory and Office Buildings

                            • Work will be underway this Saturday, April 27 starting at 7 a.m.  

                                                 Welding and surveying will be taking place. 

                            • The two tower cranes are operating and structural steel continues to be delivered and installed on both the east and west buildings.  

                            Greenway

                            • This section of the site is currently being used for laydown space.

                            Treehouse Conference Center

                            • Work will take place this Saturday, April 27, starting at 7 a.m.  

                                                 Crews will be preparing for placements. 

                                                 Masons will be working on the core. 

                                                 A crane will be operating on site.  

                            • Work is underway on the elevator cores with a concrete wall placement next week. 

                            • Underground utility work is taking place inside the site.  

                            • Temporary power is being installed on site. Eversource and crews will intermittently be working on site and off Western Avenue.   

                            Building Mock-Ups

                            • Punchlist work is ongoing on all five mockups.  

                            General

                            • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                            • Drones will be in use bi-weekly to monitor construction progress on site.

                                                 Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations. 

                                                 Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                           weekly. 

                                                 A drone flight is scheduled for Thursday at 7 a.m. 

                            Anthony D'Isidoro

                            unread,
                            May 5, 2024, 8:44:56 AMMay 5
                            to Anthony D'Isidoro
                            Enterprise Research Campus Update #39 (Week of May 6, 2024) 

                            May 3, 2024 


                            As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                            Residential/Hotel

                            • Work will be underway this Saturday, May 4, starting at 7 a.m.

                                          Utility tie-ins will be underway inside the site on Trotting Avenue.

                                          Crews will be preparing for concrete placements and steel erection.

                                          Tower cranes will be operational.

                            • Structural steel continues to be delivered and installed at the hotel, rising up beyond level eight.

                            • Concrete operations are ongoing.

                            • Utility tie-ins continue inside the site on Trotting Avenue.

                            • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                            • Visible work is underway with work progressing to level seven and eight of the high rise and midrise residential buildings.

                            Laboratory and Office Buildings

                            • Work will be underway this Saturday, May 4, starting at 7 a.m.

                                          Welding and bolting steel will be taking place.

                            • The two tower cranes are operating and structural steel continues to be delivered and installed on both the east and west buildings.

                            Greenway

                            • This section of the site is currently being used for laydown space.

                            Treehouse Conference Center

                            • Work will take place this Saturday, May 4, starting at 7 a.m.

                                          Crews will be preparing for placements.

                                          Masons will be working on the core.

                                          A crane will be operating on site.

                            • Work is underway on the elevator cores with a concrete wall placement next week.

                            • Final inspections and connections for temporary power is taking place on site. Eversource may intermittently be on site and off Western Avenue.

                            Building Mock-Ups

                            • Punchlist work is ongoing on all five mockups.  

                            General

                            • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                            • Drones will be in use bi-weekly to monitor construction progress on site.

                                          Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                          No drone flight is scheduled this week.

                                          Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                            weekly.

                              

                            CONTACT US 

                            Anthony D'Isidoro

                            unread,
                            May 11, 2024, 11:36:14 AMMay 11
                            to Anthony D'Isidoro
                            Enterprise Research Campus Update #40 (Week of May 13, 2024) 

                            May 10, 2024 


                            As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                            Residential/Hotel

                            • Work will be underway this Saturday, May 13, starting at 7 a.m.

                                            Crews will be preparing for concrete placements and steel detailing.

                                            Tower cranes will be operational.

                            • Structural steel continues to be delivered and installed at the hotel, rising up to Level 10.

                            • Concrete operations are ongoing.

                            • Utility tie-ins continue inside the site on Trotting Avenue.

                            • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                            • Visible work is underway with work progressing to level eight and nine of the high rise and midrise residential buildings.

                            Laboratory and Office Buildings

                            • Work will be underway this Saturday, May 13, starting at 7 a.m.

                                            Crews will be erecting steel.

                              • The two tower cranes are operating and structural steel continues to be delivered and installed on both the east and west buildings.

                              • Concrete placements will take place on the first floor and on the ramp.

                              Greenway

                              • This section of the site is currently being used for laydown space.

                              Treehouse Conference Center

                              • Work will take place this Saturday, May 13, starting at 7 a.m.

                                              Crews will be preparing for placements.

                                              Masons will be working on the core.

                                              Two cranes are operating on site.

                                • Work is underway on the elevator cores with a concrete wall placement next week.

                                • Crews are preparing for mass timber install later this month.

                                • Final inspections and connections for temporary power are expected. Eversource may intermittently be on site and off Western Avenue.

                                Building Mock-Ups

                                • Punchlist work and other adjustments are ongoing on all five mockups.

                                General

                                • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                                • Drones will be in use bi-weekly to monitor construction progress on site.

                                               Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                               Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                           weekly.

                                               The drone flight is planned for Thursday, May 16 at 7 a.m.

                                Anthony D'Isidoro

                                unread,
                                May 18, 2024, 8:54:20 AMMay 18
                                to Anthony D'Isidoro
                                Enterprise Research Campus Update #41 (Week of May 20, 2024) 

                                May 17, 2024 


                                As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                                Residential/Hotel

                                • Work will be underway this Saturday, May 18, starting at 7 a.m.

                                                  Crews will be preparing for concrete placements and steel detailing.

                                                  Tower cranes will be operational.

                                • Concrete operations are ongoing.

                                • A concrete placement at the mid-rise residential building is scheduled for an early start at 5:30 a.m. on Friday, May 25.

                                • Steel detailing will take place at the hotel, now up to Level 10.

                                • Utility tie-ins continue inside the site on Trotting Avenue.

                                • Intermittent use of power trowels for concrete finishing may take place after 6 a.m.

                                • Visible work is underway with work progressing to level eight and nine of the high rise and midrise residential buildings.

                                  Laboratory and Office Buildings

                                  • A small crew will maintain site operations on Saturday, May 18.

                                  • Concrete operations continue with deck placements beginning next week.

                                  • The two tower cranes are operating, and structural steel continues to be delivered and installed on both the east and west buildings.

                                  Greenway

                                  • This section of the site is currently being used for laydown space.

                                  Treehouse Conference Center

                                  • Work will take place this Saturday, May 18.

                                                    Crews will be removing scaffolding.

                                                    Masons will be working on the core.

                                                    A crane will be operating on site.

                                  • Crews will also be removing scaffolding on Sunday, May 19 starting at 7 a.m.

                                  • Work is underway on the elevator cores with a concrete wall placement next week.

                                  • Backfilling operations are ongoing.

                                  • Crews are preparing for mass timber install later this month.

                                  • Final inspections and connections for temporary power are expected. Eversource may intermittently be on site and off Western Avenue.

                                  Building Mock-Ups

                                  • Punchlist work and other adjustments are ongoing on all five mockups.

                                  General

                                  • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.

                                  • Drones will be in use bi-weekly to monitor construction progress on site.

                                                  Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.

                                                  Flights are weather dependent and are scheduled Wednesdays, Thursdays or Fridays from 7 a.m. to 9 a.m. alternating                            weekly.

                                                  No drone flight is expected this month.

                                  Anthony D'Isidoro

                                  unread,
                                  May 25, 2024, 7:09:56 PMMay 25
                                  to Anthony D'Isidoro
                                  Enterprise Research Campus Update #42 (Week of May 27, 2024) 

                                  May 24, 2024 


                                  All sites will not be working on the Memorial Day holiday on Monday, May 27, 2024.


                                  As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

                                  Residential/Hotel
                                  • Concrete operations are ongoing.
                                  • Steel detailing will take place at the hotel, now up to Level 10.
                                  • Utility tie-ins continue inside the site on Trotting Avenue.
                                  • Work is progressing to level eight and nine of the high rise and midrise residential buildings.
                                  Laboratory and Office Buildings
                                  • Concrete operations continue with deck placements.
                                  • The two tower cranes are operating, and structural steel continues to be delivered and installed on both the east and west buildings.
                                  • The east building steel is up to level 3 and the west building is up to level 6.
                                  Greenway
                                  • This section of the site is currently being used for laydown space.
                                  Treehouse Conference Center
                                  • Work will take place this Saturday, May 25 starting at 7 a.m.
                                                  Crews will be preparing the site for mass timber.
                                                  A dumpster will be swapped out.
                                  • Crews will begin installing mass timber on Tuesday, May 28.
                                  • Work continues on the elevator cores with a concrete wall placement next week.
                                  • Final inspections and connections for temporary power are expected. Eversource may intermittently be on site and off Western Avenue.
                                  Building Mock-Ups
                                  • Punchlist work and other adjustments are ongoing on all five mockups.
                                  General
                                  • The site’s four tower cranes have been erected. Three will be operational this week. They are designed to move or “weathervane” in the wind.
                                  • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                  • Intermittent use of power trowels for concrete finishing may take place after 6 p.m.
                                  • Drones will be in use bi-weekly to monitor construction progress on site.
                                                  Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                  Flights are weather dependent and are scheduled weekdays from 7 a.m. to 9 a.m. alternating weekly.
                                                  A drone flight is scheduled for Tuesday, May 28 at 7 a.m.

                                  Anthony D'Isidoro

                                  unread,
                                  Jun 2, 2024, 8:24:56 AMJun 2
                                  to Anthony D'Isidoro
                                  Enterprise Research Campus Update #43 (Week of June 3, 2024) 

                                  May 31, 2024 


                                  As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                                  Residential/Hotel
                                  • Preparation for weekday concrete placements will take place this Saturday, June 1 starting at 7 a.m.
                                  • Concrete operations are ongoing.
                                  • Steel detailing will take place at the hotel, now up to Level 10.
                                  • Utility tie-ins continue inside the site on Trotting Avenue and at Western Avenue.
                                  • Concrete will be placed at the mechanical penthouse atop the midrise residential building.
                                  • The hoist (exterior construction elevator) is being installed on the Trotting Avenue side of the midrise.
                                  • Work is progressing to level 10 of the high-rise building.
                                  Laboratory and Office Buildings
                                  • Work will take place this Saturday, June 1 starting at 7 a.m.
                                                          Steel detailing will take place.
                                                          Crews will be saw cutting concrete on lower levels.
                                                          Rebar will be installed in preparation for deck placements.
                                    • Concrete operations continue with deck placements.
                                    • Structural steel continues to be delivered and installed on both the east and west buildings.
                                    • The east building steel is up to level 4 and the west building is up to level 7.
                                    Greenway
                                    • This section of the site is currently being used for laydown space.
                                    Treehouse Conference Center
                                    • Work will take place this Saturday, June 1 starting at 7 a.m.
                                                           Crews will continue mass timber and core work.
                                    • Mass timber installation is underway with two trailer deliveries per week.
                                    • Core completion activity continues.
                                    • Final inspections and connections for temporary power are expected. Eversource may intermittently be on site and off Western Avenue.
                                    Building Mock-Ups
                                    • Punchlist work and other adjustments are ongoing on all five mockups.
                                    General
                                    • The site’s four tower cranes have been erected. Three will be operational this week. They are designed to move or “weathervane” in the wind.
                                    • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                    • Intermittent use of power trowels for concrete finishing may take place after 6 p.m.
                                    • Drones will be in use bi-weekly to monitor construction progress on site.
                                                          Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                          Flights are weather dependent and are scheduled weekdays from 7 a.m. to 9 a.m. alternating weekly.
                                                          No drone flight is scheduled this week.


                                    Anthony D'Isidoro

                                    unread,
                                    Jun 10, 2024, 9:19:27 AMJun 10
                                    to Anthony D'Isidoro
                                    Enterprise Research Campus Update #44 (Week of June 10, 2024) 

                                    June 7, 2024 


                                    As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                                    Residential/Hotel
                                    • Preparation for weekday concrete placements will take place this Saturday, June 8 starting at 7 a.m.
                                    • Concrete operations continue.
                                    • Steel installation will continue at the hotel.
                                    • Concrete will be placed at the mechanical penthouse atop the midrise residential building.
                                    • The hoists (exterior construction elevators) and loading docks are being installed.
                                    • Work is progressing to level 10 of the high-rise building.
                                    • MEP work is ongoing.
                                    Laboratory and Office Buildings
                                    • Concrete operations continue with deck placements.
                                    • Structural steel continues to be delivered and installed on both the east and west buildings.
                                    • The east building steel is up to level 4 and the west building is up to level 7.
                                    Greenway
                                    • This section of the site is currently being used for laydown space.
                                    Treehouse Conference Center
                                    • Work will take place this Saturday, June 8 starting at 7 a.m.
                                                       Masons will be working on the core and breaking down scaffolding.
                                      • Mass timber installation is underway with two trailer deliveries per week.
                                      • Core completion activity continues, expecting two concrete placements next week on Monday and Friday, weather permitting.
                                      • Final inspections and connections for temporary power are complete. Generators will be removed from site.
                                      Building Mock-Ups
                                      • Punchlist work and other adjustments are ongoing on all five mockups.
                                      General
                                      • The site’s four tower cranes have been erected. Three will be operational this week. They are designed to move or “weathervane” in the wind.
                                      • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                      • Intermittent use of power trowels for concrete finishing may take place after 6 p.m.
                                      • Drones will be in use bi-weekly to monitor construction progress on site.
                                                         Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                         Flights are weather dependent and are scheduled one weekday morning alternating weekly.
                                                         A drone flight will take place on Thursday, June 13 at 6 a.m.

                                      Anthony D'Isidoro

                                      unread,
                                      Jun 18, 2024, 10:31:22 PMJun 18
                                      to Anthony D'Isidoro
                                      Enterprise Research Campus Update #45 (Week of June 17, 2024) 

                                      June 14, 2024 


                                      As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                                      Residential/Hotel
                                      • A tower crane will be assisting steel installation this Saturday, June 15 starting at 7 a.m.
                                      • Concrete decking and other operations continue.
                                      • Steel installation progresses to level 12 at the hotel.
                                      • The mid-rise residential building has topped off.
                                      • The hoists (exterior construction elevators) and loading docks are being installed.
                                      • Work is progressing to level 10 of the high-rise building.
                                      • MEP work is ongoing.
                                        Laboratory and Office Buildings
                                        • Steel detailing will take place this Saturday, June 15 starting at 7 a.m.
                                        • Concrete operations continue with deck placements.
                                        • Structural steel continues to be delivered and installed on both the east and west buildings.
                                        • The east building steel is up to level 5 and the west building is beyond level 7, working on the first roof floor.
                                        Greenway
                                        • This section of the site is currently being used for laydown space.
                                        Treehouse Conference Center
                                        • Work will take place this Saturday, June 15 starting at 7 a.m.
                                                          Prepping for concrete placements.
                                        • Mass timber installation continues with two trailer deliveries per week.
                                        • Core completion activity continues, expecting final concrete placement.
                                        • Backfilling/flow fill will take place.
                                        • Generators are mostly removed from site as temp power is operational.
                                        Building Mock-Ups
                                        • Punchlist work and other adjustments are ongoing on all five mockups.
                                        General
                                        • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
                                        • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                        • Intermittent use of power trowels for concrete finishing may take place after 6 p.m.
                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                          Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                          Flights are weather dependent and are scheduled one weekday morning alternating weekly.
                                                          No drone flight this week.

                                        Anthony D'Isidoro

                                        unread,
                                        Jun 22, 2024, 12:53:58 PMJun 22
                                        to Anthony D'Isidoro
                                        Enterprise Research Campus Update #46 (Week of June 24, 2024) 

                                        June 21, 2024 


                                        As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.


                                        Residential/Hotel
                                        • This Saturday, June 22 starting at 7 a.m. a tower crane will be assisting to jump safety nets, and some workers will be active on building floors.
                                        • Concrete decking and other operations continue.
                                        • Hotel steel installation progresses to level 17 with work continued to periscope, the cantilevered section of the building.
                                        • The mid-rise residential building has topped off at their mechanical penthouse at level 9.
                                        • The hoists (exterior construction elevators) and loading docks are being installed.
                                        • Work is progressing to level 13 of the high-rise building.
                                        • Utility tie-in work will progress inside the fence near Western Avenue.
                                        • MEP work is ongoing.
                                        Laboratory and Office Buildings
                                        • A small crew of laborers will be working Saturday, June 22 starting at 7 a.m.
                                        • Concrete operations continue with deck placements.
                                        • Structural steel continues to be delivered and installed on both the east and west buildings.
                                        • The east building steel is up to level 5 and the west building is beyond level 7, working up to the second mechanical penthouse at level 9.
                                        Greenway
                                        • This section of the site is currently being used for laydown space.
                                        Treehouse Conference Center
                                        • A crew will be backfilling this Saturday, June 22 starting at 7 a.m.
                                        • Mass timber installation continues with two trailer deliveries per week.
                                        • Core completion activity continues.
                                        • Backfilling/flow fill will take place.
                                        • Generators are mostly removed from site as temp power is operational.
                                        Building Mock-Ups
                                        • Punchlist work and other adjustments are ongoing on all five mockups.
                                        General
                                        • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
                                        • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                        • Intermittent use of power trowels for concrete finishing may take place after 6 p.m.
                                        • Drones will be in use bi-weekly to monitor construction progress on site.
                                                              Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                              Flights are weather dependent and are scheduled one weekday morning alternating weekly.
                                                              A drone flight will take place this Wednesday at 7 a.m. and in the afternoon.

                                        Anthony D'Isidoro

                                        unread,
                                        Jun 30, 2024, 9:46:45 AM (8 days ago) Jun 30
                                        to Anthony D'Isidoro
                                        Enterprise Research Campus Update #47 (Week of July 1, 2024) 

                                        June 28, 2024 


                                        All sites will not be working on Independence Day on Thursday, July 4, 2024.  


                                        As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

                                        Residential/Hotel
                                        • This Saturday, June 29 starting at 7 a.m. a tower crane will be assisting hotel steel installation and detailing. Hoist erection will take place at the hotel. Stone grading will be underway in the basement. Some workers will be framing on residential floors.
                                        • Concrete decking and other operations continue.
                                        • Hotel steel installation up to level 17 continues with work on the periscope, the cantilevered section of the building.
                                        • The mid-rise residential building has topped off at their mechanical penthouse at level 9.
                                        • The hoists (exterior construction elevators) and loading docks are being installed.
                                        • Work is progressing to level 13 of the high-rise building.
                                        • Utility tie-in work will progress inside the fence near Western Avenue.
                                        • MEP work is ongoing.
                                          Laboratory and Office Buildings
                                          • Steel detailing will be taking place on Saturday, June 29 starting at 7 a.m.
                                          • Concrete operations continue with deck placements.
                                          • Structural steel continues to be delivered and installed on both the east and west buildings.
                                          • The east building steel is up to level 6 and the west building is beyond level 7, working up to the second mechanical penthouse.
                                          • Duct bank installation will be underway on the perimeter of the site.
                                          Greenway
                                          • This section of the site is currently being used for laydown space.
                                          Treehouse Conference Center
                                          • A crew will be removing core scaffolding and forms this Saturday, June 29 starting at 7 a.m.
                                          • Mass timber installation continues with two trailer deliveries per week.
                                          • Core completion activity continues.
                                          • Backfilling/flow fill will take place.
                                          Building Mock-Ups
                                          • Punchlist work and other adjustments are ongoing on all five mockups.
                                          General
                                          • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
                                          • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                          • Intermittent use of power trowels for concrete finishing and layout for concrete placement may take place after 6 p.m.
                                          • Drones will be in use bi-weekly to monitor construction progress on site.
                                                             Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                             Flights are weather dependent and are scheduled one weekday morning alternating weekly.
                                                             No drone flights are scheduled this week.

                                          Anthony D'Isidoro

                                          unread,
                                          Jul 6, 2024, 8:58:37 PM (yesterday) Jul 6
                                          to Anthony D'Isidoro
                                          Enterprise Research Campus Update #48 (Week of July 8, 2024) 

                                          July 5, 2024 


                                          All sites will not be working on Independence Day on Thursday, July 4, 2024


                                          As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference.

                                          Residential/Hotel
                                          • This Saturday, July 6, starting at 7 a.m., a tower crane will be assisting hotel steel installation and detailing. Mid-rise and high-rise exterior wall sheathing will be installed.
                                          • Concrete decking and other operations continue.
                                          • Hotel steel installation has topped off at level 17 and continues with work on the periscope, the cantilevered section of the building.
                                          • The mid-rise residential building has topped off at their mechanical penthouse at level 9.
                                          • The hoists (exterior construction elevators) and loading docks are being installed. The mid-rise hoist will be operational after inspections and approvals next week.
                                          • Work is progressing to level 14 of the high-rise building.
                                          • MEP work is ongoing.
                                          Laboratory and Office Buildings
                                            • Concrete operations continue with deck placements.
                                            • Structural steel continues to be delivered and installed on the east building with the west building topping off next week.
                                            • The east building steel is up to level 7, and the west building is beyond level 7, finishing the second mechanical penthouse.
                                            • Duct bank installation will be underway on the perimeter of the site.
                                            Greenway
                                            • This section of the site is currently being used for laydown space.
                                            Treehouse Conference Center
                                            • A crew will be backfilling this Saturday, July 6 starting at 7 a.m.
                                            • Mass timber detailing is underway with the next delivery planned for Friday, July 12.
                                            • Scaffolding removal and core connection work will be underway.
                                            • Stairwell concrete work will take place.
                                            Building Mock-Ups
                                            • Punchlist work and other adjustments are intermittent on all five mockups.
                                            General
                                            • The site’s four tower cranes have been erected and are operational. They are designed to move or “weathervane” in the wind.
                                            • The projects’ work hours are Monday through Friday, 7:00 a.m. and 6:00 p.m. and Saturdays as permitted by the City of Boston from 7:00 a.m. to 6:00 p.m.
                                            • Intermittent use of power trowels for concrete finishing and layout for concrete placement may take place after 6 p.m.
                                            • Drones will be in use bi-weekly to monitor construction progress on site.
                                                                 Drones will be operated by licensed pilots in accordance with Harvard University and the City of Boston regulations.
                                                                 Flights are weather dependent and are scheduled one weekday morning alternating weekly.
                                                                 A drone flight will take place on Thursday, July 11 at 7 a.m.