Allston Labworks Construction Update (December 7, 2023)

8 views
Skip to first unread message

Anthony D'Isidoro

unread,
Dec 7, 2023, 8:46:00 PM12/7/23
to Anthony D'Isidoro
llston

 

WESTERN AVENUE | ALLSTON

PROJECT CONSTRUCTION UPDATES

 

 

 

2 Week Lookahead

 

*There is work scheduled this Saturday, 12/9

 

250 Western Ave. 

 

Saturday 12/9/23

·     Large mobile crane to be erected during the day. Expect minimal traffic impacts on Western Ave. Crane to remain inside site fence for approximately 1 week.

Week of 12/11/23

·     Exterior facade work will continue.

·     Deliveries expected every day at Gates B and C

·     Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

·     Mobile crane will be onsite to hoist large mechanical equipment - will be within confines of site for approx 1 week

Next week 12/18/23

·     All tasks will be performed above.

·     Exterior facade work will continue. (*)

·     Deliveries expected every day at Gates B and C

·     Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

 

280 Western Ave.

 

Week of 12/11/23

·     Work on the Tunnel between 250 and 280 on going.

·     Deliveries expected every day.

·     Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

·     Trenching at Gate A is underway.

·     Metal panel installation work underway on the west side of the garage.

Next Week 12/18/23

·     All tasks will be performed above.

 

305 Western Ave. 

 

Week of 12/11/23

·     Steel erection and deliveries ongoing

·     Trucks will offload along the southern gates, off Western Ave.

·      Misc delivery trucks (18 wheelers) will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St. (***#))

Concrete Pours

·     12/11/2023 along McDonald

·     12/13/2023 along McDonald

·     12/15/2023 along McDonald

Next Week 12/18/23

·     All tasks will be performed above

·     Concrete pour specifics are TBD

Concrete Pours

·     12/18/2023 along McDonald

 

Upcoming Traffic Impacts

 

Saturday 12/9/23

·     Large mobile crane to be erected during the day at 250 Western Ave. Minimal traffic impacts on Western Ave. Crane to remain inside site fence for approximately 1 week.

Week of 12/11/23

·     Mobile crane will be onsite to hoist large mechanical equipment - will be within confines of site for approx 1 week

Week of 12/26/23

·     Everett Street impact for erection of man/material hoist at 305 Western Ave (one lane closure on Everett)

December 2023 (dates TBD)

·     Eversource is planning additional work on Riverdale near Harvard Teele Hall. Eversource is coordinating directly with their subcontractors. Start date not yet determined

 

 