Allston Labworks Construction Update (November 10, 2023)

10 views
Skip to first unread message

Anthony D'Isidoro

unread,
Nov 10, 2023, 9:17:22 AM11/10/23
to Anthony D'Isidoro

 

WESTERN AVENUE | ALLSTON

PROJECT CONSTRUCTION UPDATES

 

 

 

2 Week Lookahead

 

*Work is scheduled for this Sunday, 11/12

 

250 Western Ave. 

 

Week of 11/13/23

- Exterior facade work will continue. (*)

- Deliveries expected every day at Gates B and C

- Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

- Concrete placement scheduled 11/16/23. (##)

 

Next week 11/20/23

All tasks will be performed above.

- Exterior facade work will continue. (*)

- Deliveries expected every day at Gates B and C

- Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

- Concrete placement scheduled 11/21/23. (##)

 

Sunday 11-12-23

- Hoist will be extended onto the roof level from level 6.

 

280 Western Ave.

 

Week of 11/13/23

-Window installation on Level 2 and 3 underway.

-Exterior sheathing and AVB ongoing.

-Exterior facade work ongoing on west side of the garage.

-Deliveries expected every day at Gates A and B

-Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St. (***#)

 

Week of 11/20/23

-All tasks will be performed above.

 

305 Western Ave. 

 

Week of 11/13/23

- Steel erection and deliveries ongoing

- Trucks will offload along the southern gates, off Western Ave.

 - Misc delivery trucks (18 wheelers) will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St. (***#))

- Concrete Pours

- 11/15/23 and 11/16/23 - McDonald Ave will be completely closed for a concrete pours

- Mockup removal at 287 Western Ave

 

Next Week 11/20/23

- All tasks will be performed above

 

 

Upcoming Traffic Impacts

 

December 2023

- 250 Western Ave - Mobile crane will be brought to site to hoist large mechanical equipment - will be within confines of site for approx 2 weeks

 

 

Stay Connected

 

Please reach out to the team with any project site questions or concerns.

 

Westernavenueproject.com

646-679-3534



 

 