Due to weather related scheduling impacts, the Holmes Run trail surface maintenance was delayed and is scheduled to occur between May 2 - June 30, weather permitting.
- Asphalt repairs/repaving are planned for May 2 - May 19.
- Striping is planned for June 1 - 30, pending completion of asphalt repairs and asphalt curing.
Please be reminded the maintenance activities may require interim closures of small portions of the trail from a few minutes to a few hours as work is implemented. We apologize for any potential short-term inconvenience and appreciate your patience and cooperation.