to D Taniguevalene Puducherry, Rampal Singh, SG GEBEA, Shailendra Dubey, CHAIRMAN AIPEF, dalj...@gmail.com, Lukesh Thakur HP, TNEBEA, p rathanakar rao, SANJOY BHUNIA WB, Sanjay Thakur SEA, Anil Vyas, Kartikeya Dubey, CESA EA ODISHA, N. C. Mathews, Vinod Gupta, Y S Tomar, Telangana State PEA, Yash Pal Sharma, B. L. Yadav Bihar, Mohan Gangadharan Kerala, KEBEA ENGINEER, Suneel Jagtap, S K Makker, Gen Secty PSEBEA, PRESIDENT KEBEA, Ajoy Kumar Das Assam, Vinay Pandey, SURYAKANT PAWAR MAHA, A. N. Mishra..JSEB, Odisha PEA, Ashok Rao, PRASHANT CHATURVEDI..., APSEB EA, L Ravi, Irshad Wani J&K, Jayanthi T., vikaskum...@yahoo.co.in, Grover, L R DAS Orissa, SUBHRENDU SARKAR, K N Mohan, Shantanu Dixit Prayas, SECRETARY WBSEBEA, K B Dange, surinder loomba, Praveen Raj Saxena Raj, Shah Nawaz Ali Ahmed, B M Verma, H S Bedi ., MOHD SHEREEF KERALA, TSECLEA Tripura, PESA BIHAR, T S Negi THDC, aipef, E.A.S.Sarma, G. MATHEW KERALA, Er. Rajesh Pandey Chhatisgarh, MPEB Abhiyanta Sangh, K D Bansal, E. A. S. Sarma, Mukesh Kumar Uttar, Jharkhand PESA, Apparswamy K, HITESH TIWARI, Sea Mseb, G. Ramakrishnudu, S R Sitapara Guj, Munshi Majid Ali J&K, J&K EEGA, Subir Deb TRIPURA, sea mahadiscom, Jambu Khot, Jagannath Bariki, A K Jain, Subhash Rathod SEA, J K Bhanu Bihar, Pavan Jain, M. P. Singh J&k, Padamjit, P. SAHKHAR MEGHALAYA, N. J. Yagnik, Aman Mishra WB, M V Guruvadeyar SEA, Abba Saheb Morale, N J Rathod Guj, S. K. MUKERJEE, aipef INDIA, Mohan Kalluraya, Subhakanta Tripathy Odisha, Amit Ranjan Uttarakhand, Bidyut Bera WB, Pir Zada, Prayas Pune, Anand Tiwari, rahul channa, E. Mohammed Kerala, Anil Nagar, Lokesh Thakur HP, S G Datta WB, Prasanta Pattanayak, Tanvir Hasan Syed WB, Brahma Prakash ODISHA, Bikramaditya Das Assam, K K Malik, Er. Dinesh Chandra Chandra Dixit, V. S. BIDARI KARNATAK, SRINATH REDDY, A P Singh CG, Ajay Pal Singh Atwal, Anil Mishra UPCL, VENKAT SIIVREDDY, R B Savaliya GEB, Jasbir Singh Dhiman PSEBEA, RAMESHWAR MAHURE SEA, Devinder Goyal, M. Thanigivelu TN
https://www.livemint.com/industry/energy/more-than-30-gw-of-generation-capacity-out-of-commission-as-power-demand-soars-11718970291959.html

More than 30 GW of generation capacity out of commission as power demand soars

  • According to data from the Grid Controller of India, there has been a ‘generation outage’ of more than 30 GW on all but two days since May 18.
  • The delayed monsoon is partly to blame, as many plants have been unable to conduct scheduled maintenance amid elevated demand.
  • New Delhi: More than 30 gigawatts (GW) of India's power-generation capacity has been out of service over the past month even as scorching temperatures have caused the demand for power to soar. 

    According to data from the Grid Controller of India, there has been a ‘generation outage’ of more than 30 GW on all but two days since May 18. There was a 44 GW outage on 23 May and a 39 GW outage on 20 June.

    ‘Generation outage’ is the industry jargon for when power-generation capacity is out of service. It includes planned outages, including those for maintenance work, and unplanned outages due to faults.

    Shailendra Dubey, chairman of the All India Power Engineers Federation (AIPEF), said, "The capacity under outage is significant given the high demand... Peak demand is generally seen in September, not in May and June as we have seen this year. Normally, the monsoon arrives (in north India) by this time, easing demand and allowing power plants to conduct scheduled maintenance. 

  • "But this year the monsoon has been delayed, keeping demand elevated and causing several plants to defer maintenance, which will have led to faults and tripping.” 

    Power demand has remained elevated – largely in the range of 230-240 GW – after hitting an all-time high of 250 GW on 30 May.

Here a trip, there a trip…

  • Several instances of tripping have been reported from across India in the past two months. On 17 June the Northern Region Load Despatch Centre (NRLDC) reported multiple tripping incidents across Punjab, Haryana, Uttar Pradesh, Rajasthan, Delhi, Uttarakhand and Himachal Pradesh, leading to a load loss of 16.51 GW.

    Meanwhile, capacitive reactionary units are yet to be installed in a few plants, choking the supply of new generation capacity, two people aware of the development told Mint.  These units, required for grid stability, were suggested by Central Electricity Authority (CEA).