Mike, 

Is there any way to run Monte Carlo stress testing after I have found some good possible strategies?

I would like to run Builder without stress testing, and find 5 to 10 Top Results strategies.  Then, on just those good candidates, I would like to run the Monte Carlo stress testing.

Is there any way to do that?  That would save a huge amount of time by not running Monte Carlo during the normal build process.

Let me know if this is possible.

Thanks,
John

MikeBryant

unread,
Oct 30, 2024, 12:32:32 PM10/30/24
to Adaptrade Builder
Certainly. As it states in the user's guide (Build Settings, Stress Testing):

"Stress testing can either be applied during the build process or after-the-fact when re-evaluating a strategy using the Evaluate command."

John Verbrugge

unread,
Oct 30, 2024, 5:11:22 PM10/30/24
to Adaptrade Builder
HI Mike,

Ok, thanks.  I will re-read that section of the manual.  I must have missed that when I read it, or didn't understand the significance. 