Context = #Openquestion #productivity #ProjectMgt

---------------------------
1> How %complete works ?
2> any example of how you have implemented it and taking advantage
3> is any one using this with burn down view, if yes how ?
-----------------------------

Tony G

unread,
Feb 26, 2016, 2:16:45 PM2/26/16
to ToDoList (AbstractSpoon) Support
The %Complete can be calculated according to Preferences>Tasks>Attribute Calculations. See checkboxes.

As one example, the %Complete can be Time Spent divided by Time Estimate. So if the estimate is 9 hours and the time spent is 132 minutes, then the %Complete is calculated as 24%.

The %Complete for a parent of subtasks can be calculated as seen in Preferences.

The %Complete can also be used in calculating the Time Remaining - look further down on that Preferences page.

You can change the display of the %Complete value in the grid using chceckboxes under Preferences>User Interface>Tasklist Attributes.

Does that answer your question?

T

amar

unread,
Feb 26, 2016, 9:58:53 PM2/26/16
to ToDoList (AbstractSpoon) Support
Thanks Tony , yes i am good  but let's keep it open for further inputs. 