Question: Completed subtasks issue while task are filtered

30 views
Skip to first unread message

trigovina

unread,
May 9, 2017, 10:54:55 AM5/9/17
to abstractspoon-t...@googlegroups.com
Hi

If i filter incompleted task and When i marked a subtask that has daily reccureence, the new created task goes up to main task, not below or above subtask that i marked.
However, if filter is cleared no problem, when subtask marked as completed, new created one goes below or above completed subtask.
I use 7.0.13 and there is no such a problem with this version.
Please can you solve it for your next updates..

Thanks.

.dan.g.

unread,
May 10, 2017, 1:14:54 AM5/10/17
to ToDoList (AbstractSpoon) Support

trigovina

unread,
May 10, 2017, 12:51:00 PM5/10/17
to ToDoList (AbstractSpoon) Support
Sure,

I have 3 main tasks and below these tasks i have subtasks that have reccurrence daily, weekly, monthly.
I have adjusted the reccurrence settings to create a new task when marked as complete.

Case : With no filter (Show All Tasks),
When i marked a subtask as complete, the new subtask is created below completed subtask. (No problem, it's ok)

Case : With filter (Show Incomplete Tasks),
When i marked a subtask as complete, the new subtask is created below Main Tasks. (It is a subtask, not a main task)
That is the problem for new versions.
I am still using 7.0.13 and no problem with that version. That's why i can not update my software.

Thanks,

.dan.g.

unread,
May 10, 2017, 8:25:05 PM5/10/17
to ToDoList (AbstractSpoon) Support

.dan.g.

unread,
Jun 10, 2017, 5:28:23 AM6/10/17
to ToDoList (AbstractSpoon) Support
Fixed in 7.1.3


On Wednesday, 10 May 2017 00:54:55 UTC+10, trigovina wrote: