Hey, I have recently updated to the 7.0.10 version and have noticed that a watch icon in the Track Time column was missing. After a bit of research I've noticed this is true only for reference tasks (e.g. copy / Paste as Reference).

I use references as subtasks under "@Action" task and is a bit confusing not to see clearly on which reference (task) the time is ticking. Screenshot attached - I'd expect a watch icon where the red arrow is pointing. It was there in the version I had before update.

Thank you!!

Blaž
2015-12-23 14_46_57-untitled1_ - ToDoList (c) AbstractSpoon.png

.dan.g.

unread,
Dec 23, 2015, 7:45:30 PM12/23/15
to ToDoList (AbstractSpoon) Support
Well caught. I'll get it fixed for 7.0.11.

.dan.g.

unread,
Dec 23, 2015, 8:38:07 PM12/23/15
to ToDoList (AbstractSpoon) Support
ps. Fixing it will also lead to a minor performance improvement so doubly good!


On Thursday, 24 December 2015 06:40:50 UTC+11, Blaz Hostnik wrote:

Blaz Hostnik

unread,
Dec 28, 2015, 2:49:21 AM12/28/15
to ToDoList (AbstractSpoon) Support
Wonderful! I'm looking forward to the update.

.dan.g.

unread,
Jan 1, 2016, 8:25:59 PM1/1/16
to ToDoList (AbstractSpoon) Support
Fixed in 7.0.11.

Tony G

unread,
Jan 4, 2016, 1:37:27 PM1/4/16
to ToDoList (AbstractSpoon) Support
Blaž, could you explain a bit more how you're using the reference task? Thanks!