For any task, change the time unit for Time Estimate. It gives us the option to
convert all of the values, so 2880 minutes becomes 48 hours. That works. But the calculation is wrong for units other than minutes to/from
hours, this might be limited to hours to/from days. It looks like other calculations are correct but I didn't try all permutations.
The issue with hours to/from days is also present in 7.1DR2. But when I first looked at this it looked like other values might be wrong too. Please check permutations.
Thanks. T
Eric
unread,
Jan 6, 2016, 6:14:05 PM1/6/16
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to ToDoList (AbstractSpoon) Support
Hi,
I use ToDolist v7.0.11 and there is another bug between time estimate on the task line and time estimate on the bottom of the screen (task property) : need to x10 to have a correct value on task line (see the picture file attached).