Hi Dan,
Thanks for the tool. I have moved myself from spreadsheet to TDL.
I'm not sure if the group rule allows me to post on a old topic. Apologies
Here is the question:
How to enumerate task IDs and parent task IDs in excel? When I tried I'm loosing the desired hierarchies.
I would prefer an option in TDL itself which would be handy.
All the above are required because the present way of adding dependency is painful if we are not using "New dependent task". Can I expect some feature graphically add dependencies? The option in Gantt chart is difficult. Similar functionality in Tree view would be better.
-Armroid