Suggestion: Option to ignore days marked as weekends when moving task bars

25 views
Skip to first unread message

Ralph Earey

unread,
Mar 1, 2017, 11:38:13 AM3/1/17
to ToDoList (AbstractSpoon) Support
E.g. Task start date 06/03/17 due date 10/03/17 (duration 5 days) is moved to start on 07/03/17 and it counts the weekends as working days for calculating the due date (in this case 14/03/17 as it counts the 11th & 12th as working days). It would be great to have the option to ignore days marked as weekends.

.dan.g.

unread,
Mar 1, 2017, 6:40:48 PM3/1/17
to ToDoList (AbstractSpoon) Support
To do this you need to change 'days' to 'weekdays' in the 'Time Estimate' field.

Ralph Earey

unread,
Mar 7, 2017, 4:08:08 AM3/7/17
to ToDoList (AbstractSpoon) Support
Thanks Dan - that's great