‘Govt can’t recover extra compensation from land allottees’

443 views
Skip to first unread message

अर्णब् मुखर्जी

unread,
May 28, 2020, 10:22:39 PM5/28/20
to YEIDA (Yamuna Expressway Industrial Development Area)


‘Govt can’t recover extra compensation from land allottees’



Rajesh Kumar Pandey | TNN | May 29, 2020, 04:56 IST


Prayagraj: The Allahabad high court on Thursday held that the state government or development authorities cannot recover from the allottees of land the extra compensation which they have to pay to the land owners whose land were acquired without prior agreement with the allottees with regard to increase in compensation to be born by such allottees of land. 

The court further held that any extra demand made by Yamuna Expressway Industrial Development Authority (YEIDA) from allottees of land in furtherance of government order dated August 29, 2014 was illegal. Hence, the court quashed all the demands raised on the basis of GO dated August 29, 2014. 

Allowing a bunch of writ petitions filed by Shakuntla Educational and Welfare Society and various other builders and trusts, a division bench comprising Justice Pankajl Mithal and Justice VC Dixit said that the issuance of the GO dated August 29, 2014 and its acceptance by YEDA is patently illegal. 

It was on August 29, 2014, that the state government passed an order mentioning that due to agitation of the farmers and legal complications, it was necessary for an out of court settlement with the farmers by offering 64.7% additional amount for their acquired land, provided they withdraw their petitions challenging the acquisition proceedings and undertakes not to institute any litigation and create any hindrance in the development work of YEIDA. 

The government directed for the payment of 64.7% additional amount to the farmers and also to recover it from the allottees of the land. It was challenged by the allottees of land.
Petitioners’ contention was that state government was recovering increased compensation from allottees of the land, though it never modified terms and conditions of contract and in absence of any modification in terms and conditions, state government has no right to recover any excess compensation from petitioners. 

“Any rights, on the basis of a concluded or final contract or lease, which have been crystallized in favour of any party cannot be taken away by framing a policy on some later date. A policy so framed would be prospective in nature and cannot affect the contracts already finalised. Any such policy which is unilaterally framed disturbing the rights which have accrued to a party would clearly be violative of Articles 14 (right to equality) of the Constitution, the petitioners contented. 



अर्णब् मुखर्जी

unread,
May 28, 2020, 10:26:48 PM5/28/20
to YEIDA (Yamuna Expressway Industrial Development Area)

HC relief to YEIDA allottees on increased compensation

CITIES Updated: May 28, 2020 23:44 IST
Jitendra Sarin
Jitendra Sarin
Hindustantimes

In a major relief to the allottees of Yamuna Expressway Industrial Development Authority (Yeida) land in Gautam Buddh Nagar district, the Allahabad High Court on Thursday said neither the state government nor the development authorities could recover the increased compensation given to farmers whose land was acquired from the allottees without any prior agreement.

Ruling that any extra demand made by Yeida from the allottees was illegal, the court quashed all such demand orders.

With this, the bench comprising Justices Pankaj Mithal and VC Dixit allowed a bunch of petitions filed by Shakuntla Educational and Welfare Society and various other builders and Trusts.

On August 29, 2014, the state government had passed an order mentioning that due to the farmers’ stir and legal complications, an out of court settlement with the farmers offering them 64.7% more compensation for their acquired land was necessary provided they withdrew their petitions challenging the acquisition proceedings. “The government directed for the payment of 64.7% additional amount to the farmers and to recover it from the allottees of the land,” said that order.

However, the petitioners’ contention was that the state government was recovering increased compensation from the allottees though it never modified terms and conditions of the contract and in the absence of the same the state government had no right to recover any excess compensation from the petitioners.

“Any rights, on the basis of a concluded or final contract or lease, which have been crystallised in favour of any party cannot be taken away by framing a policy on some later date. A policy so framed would be prospective in nature and cannot affect the contracts already finalised. Any such policy which is unilaterally framed disturbing the rights which have accrued to a party would clearly be violative of Articles 14 and 16 of the Constitution,” contented the petitioners.

Yeida representatives could not be reached for comment.



kingfisher1997

unread,
May 28, 2020, 10:46:40 PM5/28/20
to ye...@googlegroups.com
What happens now on the amounts already charged by YEIDA from the residential plot allottees?

--
---
You have received this message because you have subscribed to the Google "YEIDA" group.
 
To visit this group, please click the link http://groups.google.com/group/yeida
To post a message to this group, kindly send an email to ye...@googlegroups.com
 
You can unsubscribe from YEIDA group through our web interface or via email.
(1) To unsubscribe through web interface, please go to http://groups.google.com/group/yeida click the "Edit My Membership" link on the right-hand side of the group's homepage. Then click the "Unsubscribe".
(2) To unsubscribe from YEIDA group via email, please send an email to yeida+un...@googlegroups.com
 
For help or assistance, please contact one of the moderators: Arnab Mukherjee, Harpreet Singh Guller, Nagin Chand, Naveen Deep Sharma, Raj Yadav or Safal Suri via email: mode...@yeida.org
 
Alternatively, you may write to Safal Suri at safa...@gmail.com or speak on +919811182828 between 10 am and 5 pm.
---
You received this message because you are subscribed to the Google Groups "YEIDA (Yamuna Expressway Industrial Development Area)" group.
To unsubscribe from this group and stop receiving emails from it, send an email to yeida+un...@googlegroups.com.
To view this discussion on the web, visit https://groups.google.com/d/msgid/yeida/a5026242-38c9-4188-bbb3-c47191754fb0%40googlegroups.com.

Harendra Singh

unread,
May 29, 2020, 9:01:50 AM5/29/20
to ye...@googlegroups.com
.All allottees have already paid, they might adjust some how, it will take time.

Regards
Harendra

Kiran Moda

unread,
May 29, 2020, 9:01:56 AM5/29/20
to ye...@googlegroups.com
Is this the same amount @ 1250/- per sq mtr which is in demand as extra compensation.?

--
---
You have received this message because you have subscribed to the Google "YEIDA" group.
 
To visit this group, please click the link http://groups.google.com/group/yeida
To post a message to this group, kindly send an email to ye...@googlegroups.com
 
You can unsubscribe from YEIDA group through our web interface or via email.
(1) To unsubscribe through web interface, please go to http://groups.google.com/group/yeida click the "Edit My Membership" link on the right-hand side of the group's homepage. Then click the "Unsubscribe".
(2) To unsubscribe from YEIDA group via email, please send an email to yeida+un...@googlegroups.com
 
For help or assistance, please contact one of the moderators: Arnab Mukherjee, Harpreet Singh Guller, Nagin Chand, Naveen Deep Sharma, Raj Yadav or Safal Suri via email: mode...@yeida.org
 
Alternatively, you may write to Safal Suri at safa...@gmail.com or speak on +919811182828 between 10 am and 5 pm.
---
You received this message because you are subscribed to the Google Groups "YEIDA (Yamuna Expressway Industrial Development Area)" group.
To unsubscribe from this group and stop receiving emails from it, send an email to yeida+un...@googlegroups.com.

Safal Suri

unread,
May 29, 2020, 1:49:10 PM5/29/20
to ye...@googlegroups.com
Agree!



Sent from my Samsung Galaxy Note10+

Safal Suri

unread,
May 29, 2020, 1:57:46 PM5/29/20
to ye...@googlegroups.com
1330



Sent from my Samsung Galaxy Note10+


-------- Original message --------
From: Kiran Moda <badam...@gmail.com>
Date: 29/05/2020 6:31 pm (GMT+05:30)

Luv Jain

unread,
May 30, 2020, 4:03:48 AM5/30/20
to ye...@googlegroups.com
Sir,

Those who have done registry also, how will they get benefit of the ruling ? 

Regards,
Luv Jain 

Shiv Minocha

unread,
May 31, 2020, 4:22:31 PM5/31/20
to ye...@googlegroups.com
What they Will do those have done their registration
Reva Minocha

ASHU TALWAR

unread,
May 31, 2020, 4:22:31 PM5/31/20
to ye...@googlegroups.com
Hello Sir,

What could be the next steps? 
As majority of us have paid the same and with huge interest as well.

Best Regards
Ashu

Reply all
Reply to author
Forward
0 new messages