A County construction project to test, grout and seal joints along
approximately 33,000 linear feet of sewer main in the Village of Wilde
Lake is scheduled to begin on or about Monday, December 3. Weather
permitting the project should be completed in 90 days.
The impact on residents in the area will be minimal. Utility trucks
will be parked on the roadside and construction noise is likely.
There will be no impact on traffic during the construction.
For questions or concerns about Capital Project S-6232, contact Lisa
Brightwell, Public Works Customer Service, at
410-313-3440, or send an
e-mail to
publi...@howardcountymd.gov.