遲至今日才回應!
基本上請照pmbok的說明為準,因為就我個人看RITA的SUMMARY TABLE也看不出您所說的QC在SV之後!
如果您所憑的是Recommend changes, defect repair, preventive and
corrective actions在scope verification之後那我想您誤會RITA的意思了!
RITA的page 134也說到此點,還請 詳閱!
就算是實務上較佳的作法,也很少QC是在SV之後,如果客戶都簽名接受了那您再作QC有何意義?
On 4月12日, 上午8時37分, Jeff Her <
jeff_jy_...@hotmail.com> wrote:
> Dear Sir:
>
> Question : Scope Verification is the process of obtaining stakeholder`s formal acceptance of the completed project scope and associated deliverables. In this context, which statement related to Scope Verification is correct?
>
> Although the "B - Quality Control is generally performed before Scope Verification, but these two processes may also be done in parallel" among all 4 answers is the best choice for this question. But according to the Rita's Process Chart & the sequence of proccess flow I have learned from the summary table, I thought QC is generally performed after SV.
>
> Any comments?
>
> _________________________________________________________________
> Invite your mail contacts to join your friends list with Windows Live Spaces. It's easy!
http://spaces.live.com/spacesapi.aspx?wx_action=create&wx_url=/friend...