When I click on unplanned tasks and enter a new task, the U column is
incremented for the last task I worked on. Shouldn't it show up for
the new task?
Fredrik
unread,
Jun 20, 2011, 9:26:17 PM6/20/11
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to Pomodairo
U is unplanned items for the task you are currently working on.