Is there a way to copy a change order to an original estimate?
I see a menu item to copy a “dummy job” estimate to another job, but I don’t see anything that crosses over from c/o to original.
One of our clerks entered a very large budget as a change order instead of an estimate, and we need to move it.
Manual entry is an option of course, but if there’s an easier way …
Thanks,
Steve
--
You have received this message, because you are a subscriber of "Profitool User Group" forum. For more information please visit this group at http://www.ptug.org
To post to this group, send email to PT...@ptug.org
---
You received this message because you are subscribed to the Google Groups "Profitool User Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PT_Users+u...@googlegroups.com.
To post to this group, send email to PT_U...@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.