Dear cả nhà,

Ch có 1 câu hỏi chưa biết cách trả lời, nhờ cả nhà mình hỗ trợ nhé:
Where is the defects documented after repaired?

Thanks!
---------------------------------------------
Nguyen Si Trieu Chau
Mobile: +84903948140
---------------------------------------------

Quy Hoang Sy

unread,
Dec 25, 2012, 10:17:09 PM12/25/12
to PMPGr...@googlegroups.com
Hi Chau,

1. Process to fix defects: defined in Organizational Process Assets: Issue and defect management procedures defining issue and defect controls, issue and defect identification and resolution, and action item tracking

2. Defect, if available, logged as change request (In change Control System): Changes may include, but are not limited to the following: defect repair

3. When implement/fix a defect change request, logged results and decision to Defect Repair document: The formally documented identifi cation of a defect in a project component with a recommendation to either repair the defect or completely replace the component

Hope it help...
Quy

From: Nguyen Si Trieu Chau <trieuc...@gmail.com>
To: PMPGr...@googlegroups.com
Sent: Wednesday, December 26, 2012 8:00 AM
Subject: {Tự học PMP tại Sài gòn - Nhóm Hai Bà Trưng} Câu hỏi

--
Bạn tham khảo danh sách nhóm tại đây: https://docs.google.com/spreadsheet/ccc?key=0AqYHOgH8IKyldGtSZWYxY1NxenFaMkRzdkJfcFNkMWc#gid=0
---
Bạn nhận được thư này vì bạn đã được đăng ký vào nhóm Google Groups "Tự học PMP tại Sài gòn - Nhóm số 2".
Truy cập nhóm này tại http://groups.google.com/group/PMPGroup-02?hl=vi.
Để có thêm tùy chọn, hãy truy cập https://groups.google.com/groups/opt_out.
 
 


Nguyen Si Trieu Chau

unread,
Dec 25, 2012, 10:51:45 PM12/25/12
to PMPGr...@googlegroups.com
Many thanks anh Quý,

Em có 3 thắc mắc nhờ anh giúp đỡ:
1. Nguồn của các thông tin trên dựa vào chỗ nào trong PMBOK hay tài liệu nào vậy anh?
2. Có Defect Repair document để record lại toàn bộ?
3. OPA có rất nhiều tài liệu, policies, procedures, guidelines... Theo như anh nói thì có issue & defect managment procedures trong OPA để giải quyết các vấn đề liên quan đến defect?

Regards!
---------------------------------------------
Nguyen Si Trieu Chau
Mobile: +84903948140
---------------------------------------------



2012/12/26 Quy Hoang Sy <hoang...@yahoo.com>

Quy Hoang Sy

unread,
Dec 25, 2012, 11:01:49 PM12/25/12
to PMPGr...@googlegroups.com
Hi Chau,

Anh tra loi inline trong mail cua em nhe

Thanks,
Quy



From: Nguyen Si Trieu Chau <trieuc...@gmail.com>
To: PMPGr...@googlegroups.com
Sent: Wednesday, December 26, 2012 10:51 AM
Subject: Re: {Tự học PMP tại Sài gòn - Nhóm Hai Bà Trưng} Câu hỏi

Many thanks anh Quý,

Em có 3 thắc mắc nhờ anh giúp đỡ:
1. Nguồn của các thông tin trên dựa vào chỗ nào trong PMBOK hay tài liệu nào vậy anh?
Trong PMBOK :-), em search la ra ngay :-)

2. Có Defect Repair document
để record lại toàn bộ?
Co, theo PMBOK. Trong thuc the du an thuong co defect log (Inspection Log neu peer review, CR neu testing defects)

3. OPA có rất nhiều tài liệu, policies, procedures, guidelines... Theo như anh nói thì có issue & defect managment procedures trong OPA để giải quyết các vấn đề liên quan đến defect?
Quy trinh handle defects thuoc OPA - vi no cung la quy trinh :-): Pass-around, formal inspection, walk-through, defect handling procedure...

Nguyen Si Trieu Chau

unread,
Dec 25, 2012, 11:07:43 PM12/25/12
to PMPGr...@googlegroups.com
Thanks anh!


2012/12/26 Quy Hoang Sy <hoang...@yahoo.com>
a ra ngay :-)

Bao Quy Nguyen

unread,
Dec 26, 2012, 12:19:32 AM12/26/12
to PMPGr...@googlegroups.com
Hi

Theo minh quy trinh la nhu vay :

the defect go through Integate change control >> approved >> direct and manage Execution >> deliverble (have repaired) + approved change request >> perform quality control >> validated change (documented by defect log) + validate diliverble >> verify scope.

Xin moi nguoi cho y kien

Qui

Vào 11:07 Ngày 26 tháng 12 năm 2012, Nguyen Si Trieu Chau <trieuc...@gmail.com> đã viết:

Le Khai

unread,
Dec 26, 2012, 12:50:45 AM12/26/12
to PMPGr...@googlegroups.com

Hi all,

Mình viết lại thế này chắc dễ hiểu hơn: đi theo thứ tự từ trái qua phải:

 

M&C Project Worrk

 

Perform Integrated Change Control

 

Direct and Manage Project Execution

 

Perform Quality Control

Verify Scope

à

(Recommended) Defect repair

à

(Approved)

Defect repair

à

(Implemented)

Defect repair

(Deliverable)

 

 

 

Qua quá trình M&C Project Work, nếu xuất hiện (Recommended)  Defect repair, sẽ là input của Perform Integrated Change Control.

Ouput Perform Integrated Change Control sẽ là (Approved) Defect repair.

(Approved) Defect repair này sẽ là input cho Direct and Manage Project Execution, và output là (Implemented) Defect repair

(Implemented) Defect repair này sẽ qua các process là Perform Quality Control và Verify Scope là kết thúc nếu OK hoặc tiếp tục lặp lại chu trình với (Recommended) Defect repair mới (là output của Perform Quality Control hoặc Verify Scope).

 

Tất cả quá trình của Defect Repair được document trong  Defect Log

ĐỊnh nghĩa trong PMBOK đây:

Log. A document used to record and describe or denote selected items identified during execution of a process

or activity. Usually used with a modifier, such as issue, quality control, action, or defect.

 

Thanks & Best regards.

Lê Khải

Mobile: 0938.338.663

 

 

From: PMPGr...@googlegroups.com [mailto:PMPGr...@googlegroups.com] On Behalf Of Bao Quy Nguyen
Sent: Wednesday, December 26, 2012 12:20 PM
To: PMPGr...@googlegroups.com
Subject: Re: {Tự học PMP tại Sài gòn - Nhóm Hai Bà Trưng} Câu hỏi

 

Hi

Quy Hoang Sy

unread,
Dec 26, 2012, 4:23:54 AM12/26/12
to PMPGr...@googlegroups.com
Hi All,

Co cai nay minh chua hieu lam, nho chuyen gia giai thich bang tieng Viet dum nhe:

Funding Limit Reconciliation
The expenditure of funds should be reconciled with any funding limits on the commitment of funds
for the project. A variance between the funding limits and the planned expenditures will sometimes
necessitate the rescheduling of work to level out the rate of expenditures. This can be accomplished
by placing imposed date constraints for work into the project schedule

Thanks a lot!
Quy

From: Le Khai <ldt...@gmail.com>
To: PMPGr...@googlegroups.com
Sent: Wednesday, December 26, 2012 12:50 PM
Subject: RE: {Tự học PMP tại Sài gòn - Nhóm Hai Bà Trưng} Câu hỏi

Nguyen Si Trieu Chau

unread,
Dec 26, 2012, 4:38:04 AM12/26/12
to PMPGr...@googlegroups.com
Hi anh,

Anh xem trang 178 PMBOK, hình 7-6 nhé. Ở đây planned expenditures (hoặc cost baseline) sẽ theo S-curve, đó là số tiền dự định chi tiêu theo time-phased trong suốt dự án. Trong khi đó funds sẽ được cấp nguyên cục theo dạng bậc thang. Do đó nếu đoạn bậc thang này lẹm qua (cắt qua) đường S-curve thì có nghĩa là sẽ có giai đoạn cần trả tiền mà fund ko đủ. Vì vậy cần phải, hoặc xin thêm fund để cover hết S-curve tại mọi thời điểm, hoặc "rescheduling of work". Ý nghĩa của Funding limit reconciliation này là để đảm bảo lúc nào cũng có tiền để chi cho dự án. Cũng nói thêm là cách chi tiền cho dự án ko phải là có đầy đủ fund (FULL) từ đầu để cover cho cost baseline (hoặc cost budget nếu tính luôn cả management reserve), mà fund sẽ được chi theo time-phased

Regards!
---------------------------------------------
Nguyen Si Trieu Chau
Mobile: +84903948140
---------------------------------------------



Quy Hoang Sy

unread,
Dec 26, 2012, 4:52:44 AM12/26/12
to PMPGr...@googlegroups.com
Cam on nhieu, Chau. Nhu vay no se dan toi Update cost P baseline and/or schedule baseline ha
Quy


From: Nguyen Si Trieu Chau <trieuc...@gmail.com>
To: PMPGr...@googlegroups.com
Sent: Wednesday, December 26, 2012 4:38 PM

Nguyen Si Trieu Chau

unread,
Dec 26, 2012, 5:01:04 AM12/26/12
to PMPGr...@googlegroups.com
Theo như PMBOK thì "sometimes necessitate the rescheduling of work to level out the rate of expenditures. This can be accomplished by placing imposed date constraints for work into the project schedule" --> thay đổi schedule baseline --> thay đổi cost baseline. Đúng như anh nói!

Tuy nhiên ở thực tế thì em thường xin thay đổi funding limit vì nó dễ dàng hơn (thường thì đã được approved total budget trước, mình thay đổi thời gian xin cấp fund và báo cho các bộ phận liên quan - chủ yếu là bộ phận Finance để họ chủ động nguồn tiền và tính toán cash flow của công ty). Trong trường hợp ko thay đổi được funding limit (theo time-phased) thì chỉ còn cách update baselines.

Quy Hoang Sy

unread,
Dec 26, 2012, 5:13:50 AM12/26/12
to PMPGr...@googlegroups.com
Great! Thanks a lot, Chau!
Quy


From: Nguyen Si Trieu Chau <trieuc...@gmail.com>
To: PMPGr...@googlegroups.com
Sent: Wednesday, December 26, 2012 5:01 PM

Bao Quy Nguyen

unread,
Dec 27, 2012, 7:41:41 PM12/27/12
to PMPGr...@googlegroups.com
Chuc mung Anh Quy, Anh Khai

Vào Thứ tư, ngày 26 tháng mười hai năm 2012, Nguyen Si Trieu Chau đã viết:
--
Bạn tham khảo danh sách nhóm tại đây: https://docs.google.com/spreadsheet/ccc?key=0AqYHOgH8IKyldGtSZWYxY1NxenFaMkRzdkJfcFNkMWc#gid=0
---
Bạn nhận được thư này vì bạn đã được đăng ký vào nhóm Google Groups "Tự học PMP tại Sài gòn - Nhóm số 2".
Truy cập nhóm này tại http://groups.google.com/group/PMPGroup-02?hl=vi.
Để có thêm tùy chọn, hãy truy cập https://groups.google.com/groups/opt_out.
 
 


--


Reply all
Reply to author
Forward
0 new messages