holly avinash

unread,
Dec 1, 2024, 3:48:56 AM12/1/24
to GVI Other Series

The result of watershed analysis can only be seen in the exported picture, but not marked in the point cloud data?

GVI Other Series

unread,
Dec 1, 2024, 3:49:55 AM12/1/24
to GVI Other Series

It is recommended to classify the water area into a separate category, such as Lake, when classifying the point cloud, then add Lake detection in the "Power line Parameter Setting" and set the safety distance. Then, through the clearance danger point analysis, you can get the analysis of the water area.