Hi,

Are you aware 10 crores has been assigned to the Contractor for getting these 82 roads drain desilted, lay it with the concrete slabs and finally asphalt the roads.

This work was assigned in 2019 and the work had started only in August 2021.

Some of these roads have already started with their desilting and slab work laying.

If you ignore, contractor saves more profit for the work he has not done. Ultimately the road user will be at a loss.

But if you believe that your property tax money cannot get wasted or looted and if your road is included in this list, kindly coordinate with the Contractors Supervisor Mr. Harish 9686511589.

If you have any difficulties with the contractor team or not able to identify your road using the road id, you can get in touch with me directly.

Regards,
Amith Nigli
9449818450