Re: B-1102

34 views
Skip to first unread message

sanjeev kumar

unread,
Oct 6, 2017, 5:15:44 AM10/6/17
to Info, m...@paramountgroup.co.in, my.docu...@outlook.com, NEparamou...@googlegroups.com, NEFOWA, Mudasir Amin, sanjeev kumar

To,

Paramount Propbuild Private Limited

H123, Sector -63 Noida

Uttar Pradesh

 

Subject :- Not acceptable any unethical, illegal, false demand (4.5% GST on the payment done by customer).


Sir,


First of all any unethical, illegal, false demand will not be accepted and it will be challenged in honorable court


Why should I Pay GST? For your failure to deliver? Because since last 7 years I am paying Rent + Home Loan EMI and going through mental harassment?


I have booked this flat in August 2010  and as per my flat buyer agreement, you had to deliver the flats by max June 2014, It is more than 7 years after booking, still there is no hope to get this flat in near future, no information about  when I will  get the possession of flats.


I have paid 90% of total cost of flat without any delay from my side, whenever I received the demand I paid the due on time so that you can deliver on time.

As per law, order of court in some cased, agreement, I am supposed to receive the penalty from builder for delay in delivery as per the commitment.  So please provide delay penalty as per RERA. Please note that RERA law states that the rate builder charged from customer for delay payment + additional 2% interest, since you charged 24% interest rate so as a buyers I am supposed to get 26% interest.


Again my question is why should I be punished for your failure? Thus I will not to pay single rupees for any unethical, illegal, false demand other than mentioned in demand letter, be it GST or any other charges.

 

 


With Thanks & Regards,
Sanjeev Kumar

Technical Superintendent
Email ID-    sanj...@gmail.com

On Thu, Oct 5, 2017 at 1:27 PM, Info <in...@paramountgroup.co.in> wrote:

Dear Customer,


We are pleased to inform you that your emotions project is in the advance stage of finishing. To facilitate our customers, company as a special offer, would charge only 4.5% GST on the payment which is preponed and paid by the customer, balance burden of GST shall be borne by the company. You may avail this golden opportunity as the above scheme is valid till 31st October 2017 only. Please note that company shall not extend the scheme beyond the scheduled date.

 

Thanking You,

For Paramount Propbuild Pvt. Ltd


This is computer generated letter no authorized signature required.


P.S: Bank contact details for your reference.

Bank Name

Contact Person

Mobile Number

Tata Capital

Pradeep Kumar Tekwani

9818104020

Punjab National Bank

Rahul Rana

9810202858

ICICI Bank

Himanshu

8527504206

Axis

Harshan

9810276882

Corporation

Shivani

9599712220

 


sanjeev kumar

unread,
Dec 12, 2017, 11:03:13 AM12/12/17
to Info, my.docu...@outlook.com, NEFOWA, Mudasir Amin
Dear Sir/Madam,

I visited the site yesterday only and found the same status including water pipeline fitting in the drawing room, kitchen and master bedroom and because of that flooring work is pending in the complete flat except two bedrooms. Electrical Wiring, Water Fitting, Sanitation work, Tile work, kitchen work, door and windows work, glass work everything is pending and you people are saying Offer of Possession will be sent in Dec. 2017./Jan., 2018.

Kindly take it seriously and ask the person concerned at site to speedup the work so that our flat No.E-902 may come at par like other flats in the tower.

We are eagerly waiting for the possession to reduce unnecessary monetary burden being faced by us by paying EMI & Rent.

Thanks


With Thanks & Regards,
Sanjeev Kumar

Technical Superintendent
Email ID-    sanj...@gmail.com

On Fri, Oct 13, 2017 at 1:14 PM, Info <in...@paramountgroup.co.in> wrote:
Dear Sir,
This is in reference to your email regarding unit no :B-1102 in our project Emotions.

This is to inform you that the below scheme was launched to benefit the customers as loyality discount. As far as GST is concern, 18% GST was lievied by government wherein rebate of 6% has been given by them, which means customer is lible to pay 12% GST on the demands which wolud be raised post GST implentation. However as the good gesture, company is taking liablity of 7.5% and rest 4.5% will be born by customer till 31st October 2017. Company will assure that whole 12% GST will be payable to government,Please be informed that our project is in advance stage of finishing.

If you need any further help, please do not hesitate to get in touch. You can visit our website, 
www.paramountgroup.co.in or you can call us on 120-488-2000 between 10am to 5pm Monday to Saturday.

Your faithfully

Paramount Group