On June 18, WSDOT, Graham Contracting Ltd., Sound Transit, and City of Kirkland hosted the summer quarterly update meeting overviewing the next phases of construction and what changes to expect at the I-405 and NE 85th St Interchange Project. The meeting focused on current project status, project schedule, construction expectations in the area, night and weekend lane reductions in July, two weekend closures in Sept., and how the public can stay informed and contact the project team. The team also answered questions from community members. A recording of that meeting is available on YouTube
 and can be viewed along with other resources at bit.ly/85th-Interchange-Project near the bottom of the page under the tab "Related links."