QUESTIONS AND ANSWERS
On what basis were Five-Year Plan projects selected to be part of the
proposition and what types of projects have been included?
The District's Five-Year Plan is updated annually. Projects are
identified, prioritized and scheduled for completion during a five-
year period with respect to health and safety issues and program
needs. Projects included within the proposition represent categories
of work that had been scheduled for completion in what would have been
years one through three of the Five-Year Plan. Barring extraordinary
or unforeseen circumstances, all of these projects will be completed
by September 2012.
Some of the types of projects include roof resurfacing, municipal
water and sewer hookups, boiler replacements, bathroom renovations and
heating and ventilating upgrades. A complete list of projects by
building is included in the Master Plan edition of WCSD In Print or
you may consult the District's web site (
www.wappingersschool.org).