From: "Goran Kopic" <gnk...@rogers.com>
To: <mta...@bellnet.ca>
Subject: RE: Q8 question
Date: Wed, 27 Oct 2010 08:39:33 -0400
Makes sense!
Thanks Manoj...good luck tonight!
Goran
-----Original Message-----
From: mta...@bellnet.ca [mailto:mta...@bellnet.ca]
Sent: Wednesday, October 27, 2010 7:20 AM
To: Goran Kopic
Subject: Re: Q8 question
I believe that since the maximum for bogey quantity is 80, he will not play a 100 rounds even if offered in the contract
therefore, the equation should be: .5(80(80-0))-3400=3200-3400-200, and he picks low demand contract
--
Manoj Talwar
---- Goran Kopic <gnk...@rogers.com> wrote:
=============
Hi Manoj!
Question:
Menu C, Bogey surplus for contract 2 calculation (HD), page ¾ shows
calculation of 0.5(100(80-0))-3400=3200-3400=-200
Result is choice of LD contract by Bogey player.
I believe this calc should equal 4000-3400=600 in which case Bogey player
would choose HD contract, in which case overall profits would change…do you
agree?
Goran
=============