THIS WEEK
- (Week of 9/25)
*Work is scheduled for this Saturday 9/23
250 Western Ave.
·
Steel will be detailed on the upper floors
·
Delivery trucks will access project site via Western Ave. and/or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard
St.
·
Concrete placement scheduled 9/25
·
Exterior framing ongoing on upper floors
·
Windows will be set on the north elevation
·
Spray fireproofing ongoing on upper floors
280 Western Ave.
Saturday 9/23
·
Work is scheduled
Week of 9/25
·
Interior mechanical work ongoing in the garage
·
Framing starting on level 2 of the residential area
·
Delivery trucks will access project site via Western Ave. and/or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.
·
Concrete placement scheduled 9/27
·
Mechanical work ongoing in the residential
·
Facade work ongoing on south & west side of the garage
·
Spray fire proofing ongoing on level 4
305 Western Ave.
Saturday 9/23
·
Work is scheduled
Week of 9/25
·
Misc. Deliveries will access the project site via Western
Ave. and/or Everett Street and return to the expressway via Western Ave. No truck access on N. Harvard St.
·
Steel deliveries are ongoing. Trucks will offload along the southern gates, off Western Ave.
·
Continue mock-up construction at 287 Western Ave. lot - intermittent delivery of construction materials
UPCOMING - (Week of 10/2)
·
Continue with all activities listed above
·
Concrete placement dates at 250 Western Ave. - TBD
·
Steel will continue to be detailed on the upper floors at 250 Western Ave.
|