September 15, 2023 


As the Enterprise Research Campus (ERC) project continues, we will provide project notifications that outline upcoming and impactful activities, including a map of the area for reference. 


Crews are preparing sites for the predicted inclement weather conditions. There will be no work this Saturday with the exception to a few workers monitoring the site during the storm. 


Residential/Hotel 

  • Bulk excavation of the site continues.

  • On Monday, September 18th, soil will begin to be hauled to Beacon Park Yard.

                       Trucks will use a private haul road to transport the soil to be taken off site via rail. 

                       Soil will continue to be trucked out simultaneously. 

  • Concrete operations have mobilized on site. 

  • Crews are working to excavate a pad where the first of two tower cranes will be erected in October. 

Laboratory and Office Buildings 

  • Bulk excavation of the site continues. 

Greenway 

  • This section of the site is currently being used for laydown space until crews mobilize in the coming months. 

Treehouse Conference Center 

  • The jersey barriers and fence line has been extended onto Western Ave by Milestone Dr. 

  • Crews prepare to mobilize for construction starting at the end of September. 

Building Mock-Ups 

  • Curtainwalls have been installed on the first two of five building mockups. 

  • The screen walls will be installed at the end of the month. 