Detention / Retention Pond: Can the surface area of a detention or retention pond—whether dry-bottom or wet-bottom—be counted toward the total required green space, provided it is landscaped and visually integrated into the open space network, or would that be counted towards the buildable area?
keltingcs
unread,
Oct 28, 2025, 4:25:32 PM10/28/25
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to 2026 Production Home Building Competition
The county does not allow the inclusion
of ponds in the green space requirement calculation. The green space
requirement is for primary and secondary
active and passive greenspace areas that do not include stream buffers
and ponds.