John C Black

unread,
Sep 8, 2014, 10:50:40 PM9/8/14
to

Dustin, Richard, and the Australians installed the tail track on the new Siding on the Witcombe to Aspen run.  Then they ballasted the siding and filled in the places where the ballast was a little light.  They also installed 2 kick switch kits.  

The plan Tuesday is to put in the Switch Stand.  That will finish the Witcombe to Aspen track.

Raven cleaned in Central Station.

John

JOIN TRAIN MOUNTAIN -- http://www.TMRR.org

Fire Danger = EXTREME  http://scofmp.org/kfifc/kfifc.shtml
IFPL = Level III  http://scofmp.org/ifpl.html

Fire Watch = 3 hours
No Tracked Vehicle Operation after 1:00pm
Fire Tools & Fire Extinguishers in Trucks
Fire Truck with Water at each operation area
Oregon Landowner Fire Liability - http://www.friendstm.org/LandownerFireLiability.pdf
Fire Watch & Fire Tool Requirements - http://friendstm.org/FireToolsNotice.pdf

The lawyers continue working to resolve the Timberlake gates issue. Please be patient.
Reply all
Reply to author
Forward
0 new messages