Fab 40 is probably already being planned

0 views
Skip to first unread message

bbbl67

unread,
May 30, 2006, 11:52:27 AM5/30/06
to
The recently announced decision to upgrade Fab 30 to Fab 38, may not be
the end of it for AMD. There is enough room on the Dresden land to
build a 3rd full fab, which would probably likely be Fab 40 in 2010.

Fab 36 will be a full-capacity 300-mm fab. Fab 38 will likely be a
small-capacity 300-mm fab, producing maybe only half as much as Fab 36
can. Then Fab 40 would be another full-capacity fab. Part of the reason
that Fab 38 will be smaller capacity than the other two is because a
bump-and-test building will be built right into it which will serve the
other fabs too; this will reduce the amount of space available in Fab
38.