Fwd: Parking doing construction of New Garage Gate at The Vaux

3 views
Skip to first unread message

Paul Block

unread,
Sep 12, 2025, 2:38:00 AMSep 12
to Tim Miller, vauxof...@googlegroups.com, Bob Weinstein, Cynthia Horvath
Tim, i think we have to warn the community that if the removal of their car on the 25th has time requirements, they should park outside of the garage overnight on the night before. Meter parking ends at 9 PM I believe and doesn’t start again until 9 AM I believe.  I will check the parking timing and let you know.
And I think we have to hire Security overnight starting the night of the 25th as the gates will be down
-Paul

Sent from my iPhone

Begin forwarded message:

From: Sean Albers <Se...@metrogates.com>
Date: September 11, 2025 at 1:03:41 PM PDT
To: Paul Block <bloc...@gmail.com>, Alex Krueger <al...@metrogates.com>
Cc: Tim Miller <tim.m...@kinliving.com>, vauxof...@googlegroups.com, Adi Gonzalez <Ad...@metrogates.com>, halba...@comcast.net
Subject: Re: New Garage Gate at The Vaux


Paul, there will be very limited access with long delays on the first day the second day will offer more access but will still have some delays while everything is being configured.

Thank you,
Sean
(please forgive talk to text errors)

Sent from my Galaxy phone
Get Outlook for Android

From: Paul Block <bloc...@gmail.com>
Sent: Thursday, September 11, 2025 12:32:45 PM
To: Alex Krueger <Al...@metrogates.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com <vauxof...@googlegroups.com>; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>; Hal@Comcast <halba...@comcast.net>
Subject: Re: New Garage Gate at The Vaux
 
You don't often get email from bloc...@gmail.com. Learn why this is important
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Is the 9/25-26 date pretty solid, Alex?
-paul

On Thu, Sep 11, 2025 at 9:38 AM Alex Krueger <Al...@metrogates.com> wrote:

Hello all,

 

I wanted to give you a quick update, we are still aiming for the timing that we discussed a few weeks ago:

 

  • Thursday 9/25 – Friday 9/26

 

Please have security ready for Thursday (9/25) night while the gate is down. I will be out of office starting next Tuesday, but Sean will follow up if there are any timing changes!

 

 

 

Thanks,

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Alex Krueger
Sent: Tuesday, September 9, 2025 11:21 AM
To: Paul Block <bloc...@gmail.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>; Hal@Comcast <halba...@comcast.net>
Subject: RE: New Garage Gate at The Vaux

 

Paul,

 

Here’s the shop drawing as requested!

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Alex Krueger <Al...@metrogates.com>
Sent: Thursday, September 4, 2025 10:12 AM
To: Paul Block <bloc...@gmail.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>; Hal@Comcast <halba...@comcast.net>
Subject: RE: New Garage Gate at The Vaux

 

Thanks Paul! Looks like my to the google group are bouncing back since I’m not a part of it.

 

I’ve copied in Hal since I have his email address. You may want to send this drawing to the google group if they didn’t already receive it.

 

 

 

Thanks,

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Paul Block <bloc...@gmail.com>
Sent: Wednesday, September 3, 2025 5:33 PM
To: Alex Krueger <Al...@metrogates.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>
Subject: Re: New Garage Gate at The Vaux

 

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

Vaux officers, Hal, Joe, Tim, Diana...please respond.

I approve the gate as drawn and explained.

Do you approve?

-paul

 

On Wed, Sep 3, 2025 at 4:09PM Alex Krueger <Al...@metrogates.com> wrote:

Hey Paul & Team,

 

I wanted to follow up on this drawing and see if you have any questions. As noted, we have shown 2” x 2” mesh on the full gate. This matches the mesh that is on the current gates on the outer edges. This will make it more difficult for anyone to reach through the gate.

 

Is this approved to move forward?

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Alex Krueger
Sent: Friday, August 29, 2025 4:14 PM
To: 'Paul Block' <bloc...@gmail.com>
Cc: 'Tim Miller' <tim.m...@kinliving.com>; 'vauxof...@googlegroups.com' <vauxof...@googlegroups.com>; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>
Subject: RE: New Garage Gate at The Vaux

 

Paul,

 

I have attached a drawing for design approval! Please let me know if you have any questions or changes.

 

This will be flush with the existing front posts, and we will have the gate hinge off the back of the post (shown at the top of the drawing) to avoid the reach through area on the LH and RH sides of the gate. The arrangement will look cleaner and give you slightly more width as well. We also have put 2” x 2” x ¼” mesh along the full gate which will greatly help with reach through protection.

 

We were able to squeeze out an overall width to 15’1”, adding just over a foot compared to our conservative 14’ we spoke about initially.

 

 

 

Thanks,

 

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Alex Krueger <al...@metrogates.com>
Sent: Thursday, July 31, 2025 3:43 PM
To: Paul Block <bloc...@gmail.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com; Adi Gonzalez <Ad...@metrogates.com>; Sean Albers <Se...@metrogates.com>
Subject: RE: New Garage Gate at The Vaux

 

Paul,

 

We just got an update from Tim on Friday that the deposit is being processed, so we will hopefully see that soon!

 

I have scheduled Tuesday, 8/19 for us to take measurements with our fabricator so we can get you a drawing for approval the week of 8/25.

 

We have also blocked dates for fabrication production the first two weeks of September which will put install timing around end of September/early October.

 

We are not completing any permits for city approval, however the permits for the electrical work will be completed concurrently with the installation work.

 

 

 

Thanks,

 

 

--

Alex Krueger

Estimator

Metro Access Control

Direct: 503-946-1280

Office: 503-595-4716

Al...@metrogates.com

For sales reach out to sa...@metrogates.com

For service dispa...@metrogates.com

CCB# 46091 CC# METROOD121MJ

 

From: Paul Block <bloc...@gmail.com>
Sent: Thursday, July 31, 2025 3:23 PM
To: Alex Krueger <al...@metrogates.com>
Cc: Tim Miller <tim.m...@kinliving.com>; vauxof...@googlegroups.com
Subject: New Garage Gate at The Vaux

 

CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.

Hi Alex, are we on track for the new garage gate at the Vaux?  

And approximately when can we look at design (including approval), permit, and construction happening.

Thanks,

-paul block

Tim Ackley

unread,
Sep 12, 2025, 11:44:09 AMSep 12
to vauxof...@googlegroups.com, Tim Miller, Bob Weinstein, Cynthia Horvath
Since security coverage is necessary to support the gate replacement, my take is that the cost is part of total project cost and should be charged directly to the reserve project as a reserve expense.

Tim

--
Tim Ackley
2335 NW Raleigh Street Unit 139
Portland, Oregon 97210
 


--
Officers of The Vaux
---
You received this message because you are subscribed to the Google Groups "vauxofficers" group.
To unsubscribe from this group and stop receiving emails from it, send an email to vauxofficers...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/vauxofficers/4680E4EC-4731-4AF2-A6A5-53D191E3B8D6%40gmail.com.

Joe Mack

unread,
Sep 12, 2025, 11:53:12 AMSep 12
to vauxof...@googlegroups.com
I agree Tim. That is how it would be done in a business accounting model
Joe

wor...@finitearts.com