Puppet / Task PUP-11340
Declare Ready to Ship (go/no-go) milestone (Puppet Platform 7.13.0)
Change By: tefoji
Epic Link: PUP-11335
Add Comment Add Comment
 
This message was sent by Atlassian Jira (v8.13.2#813002-sha1:c495a97)
Atlassian logo

tefoji (Jira)

unread,
Nov 9, 2021, 7:30:03 PM11/9/21
to puppe...@googlegroups.com
tefoji created an issue
Issue Type: Task Task
Assignee: Aidan Nathanson
Created: 2021/11/09 4:29 PM
Due Date: 2021/12/06
Labels: release
Priority: Normal Normal
Reporter: tefoji

(Initial planned release date: 2021-12-07)

1) Ensure all prerequisite release tasks are complete.

2) Review the release Kanban board to ensure all tickets are resolved.

3) Ping release leads in #proj-puppet-releases Slack channel for go/no-go decision.

4) Send email indicating Ready To Ship milestone has been achieved.