I’m starting to experiment a little with my server patching. I have a group of servers that are set to auto-reboot after patching, so figured that would be the group to test with. I created an ADR, set the evaluation schedule to every 2nd Tuesday. I set up the deployment settings, made it required, set the schedule for available time at 6 days, and set the installation deadline at 7 days. I do also have a maintenance window for the collection, which has been in place forever. The ADR created the SUG as expected, and this morning I found a deployment for it. But none of the machines completed the process. They’re all showing In Progress, downloaded updates. So, logically, my thought is that the downloaded the updates on the 6th day after evaluation, but for some reason, didn’t install them on the 7th day, during the maintenance window. I verified the maintenance window is still in the correct time period, as well. Not sure where to look to try and see why they didn’t install. Any thoughts? Anyone have a good, working ADR for server patching?
Thanks,
Joe Heaton
Managed Services and Operational Support Unit
Information Technology Operations Branch
Data and Technology Division
CA Department of Fish and Wildlife
1700 9th Street, 3rd Floor
Sacramento, CA 95811
Phone: 916-919-5816
Joseph,
How long is the maintenance window on your server collection? I ran into a problem a while ago where we only had a 2-hr maintenance window (used to be open for a lot more hours) and constantly saw the same thing. I finally tracked it down to being a maintenance window that could not accommodate the estimated time each update has. The combined time of all updates exceeded the maintenance window. The main culprit, I found, was the monthly malicious software update as the estimated time for those updates is set to 120-minutes. At the time, I would just manually change the estimated time on these updates to 60-minutes, rather than 120. That worked until we changed hours and then I didn’t have to edit anything anymore cause our maintenance window is now around 5-8 hours.
Anyway, if your server collection’s maintenance window(s) are too short, you might see something like this. Good luck!
Later,
Matt Helton
(he/him/his)
Assistant System Administrator
Library Information Technology Services
Milner Library, Room 177
Illinois State University
Office: 309-438-2876
Help Desk: 309-438-8399
Help E-mail: librar...@ilstu.edu
From: ntsyste...@googlegroups.com <ntsyste...@googlegroups.com>
On Behalf Of Heaton, Joseph@Wildlife
Sent: Wednesday, May 22, 2024 08:52
To: ntsyste...@googlegroups.com
Subject: [ntsystemcenter] ADR for patching servers
|
This message originated from outside of the Illinois State University email system. Learn why this is important |
--
You received this message because you are subscribed to the Google Groups "ntsystemcenter" group.
To unsubscribe from this group and stop receiving emails from it, send an email to
ntsystemcente...@googlegroups.com.
To view this discussion on the web visit
https://groups.google.com/d/msgid/ntsystemcenter/SJ0PR09MB6686B5181FEEBF74307308F0AAEB2%40SJ0PR09MB6686.namprd09.prod.outlook.com.
I don’t think it’s the maintenance window. That’s 9 ½ hours, but it might be those estimated times… I’ll take a look at those.
From: 'Helton, Matt' via ntsystemcenter <ntsyste...@googlegroups.com>
Sent: Wednesday, May 22, 2024 7:50 AM
To: ntsyste...@googlegroups.com
Subject: [ntsystemcenter] RE: ADR for patching servers
WARNING: This message is from an external source. Verify the sender and exercise caution when clicking links or opening attachments.
To view this discussion on the web visit https://groups.google.com/d/msgid/ntsystemcenter/CH0PR03MB598836630CCC75A3E123F953AAEB2%40CH0PR03MB5988.namprd03.prod.outlook.com.
So, I learned something about ADR deployment scheduling…
I didn’t read the details when I set it up. The time in the Installation deadline area is added to the time in the available time area. So, my ADR deployment was doing exactly what I told it to. Make it available after 6 days, and then, 7 days after that is the deadline. It wasn’t going to install the updates until the 27th, lol.
To view this discussion on the web visit https://groups.google.com/d/msgid/ntsystemcenter/SJ0PR09MB6686B389AB370999CCD23976AAEB2%40SJ0PR09MB6686.namprd09.prod.outlook.com.
Easy mistake to make. Glad you got it figured out!
Matt Helton
(he/him/his)
Assistant System Administrator
Library Information Technology Services
Milner Library, Room 177
Illinois State University
Office: 309-438-2876
Help Desk: 309-438-8399
Help E-mail: librar...@ilstu.edu
From: ntsyste...@googlegroups.com <ntsyste...@googlegroups.com>
On Behalf Of Heaton, Joseph@Wildlife
Sent: Thursday, May 23, 2024 10:13
To: ntsyste...@googlegroups.com
Subject: [ntsystemcenter] RE: ADR for patching servers
|
This message originated from outside of the Illinois State University email system. Learn why this is important |
To view this discussion on the web visit https://groups.google.com/d/msgid/ntsystemcenter/SJ0PR09MB66864EFD40EE7B0CF6B7793BAAF42%40SJ0PR09MB6686.namprd09.prod.outlook.com.