Presently my tasks on my pc (not on my device) show the project listed before the text of the task in for instance "due next 7 days".  How do I eliminate the project id at the beginning of the task and instead have the text of the task at the beginning ?

Richard Emes

unread,
Mar 17, 2021, 12:45:22 PM3/17/21
to MyLifeOrganized
Hi, you need to click on Tools - Options - To-Do list format. You'll see that 'Encode project name' is checked. In the 'Notation' section, you can define where this encoding is either 'Prefix' (in your case' or 'Postfix' - the Postfix option lists the project name after the name of the tasks.

You can also define if the project name is, for example, bracketed eg put ( in Start string and ) in End string. This can help to separate the name of the project from the name of the task

Hope this helps

Richard

Bob Lynch

unread,
Mar 17, 2021, 2:12:52 PM3/17/21
to mylifeo...@googlegroups.com
Such an easy fix... thanks for taking the time to walk me through it !

--
You received this message because you are subscribed to a topic in the Google Groups "MyLifeOrganized" group.
To unsubscribe from this topic, visit https://groups.google.com/d/topic/mylifeorganized/iiDu_54p2ts/unsubscribe.
To unsubscribe from this group and all its topics, send an email to mylifeorganiz...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/0a93556f-2288-47b1-b915-a8f973b91aa7n%40googlegroups.com.
Reply all
Reply to author
Forward
0 new messages