Linking the start date on a dependent task to end date

41 views
Skip to first unread message

Ryan Sheftel

unread,
May 28, 2015, 6:27:27 AM5/28/15
to mylifeo...@googlegroups.com
Is it possible to link the start date of a task to the due date of a task it depends on. That way if I update the due date of a task, say it took longer than originally planned, then the start date (and due date if the lock period is checked) of all dependent tasks would adjust accordingly.

This would be very helpful in using MLO for project planning. thanks.

chrisleeuk

unread,
Nov 20, 2015, 3:22:11 PM11/20/15
to MyLifeOrganized
No this is not currently possible. I agree it would be useful at times, because you end up having to manually adjust the dates.
Reply all
Reply to author
Forward
0 new messages