I have the new MLO2.

I havevthe free version operating nowbin pro mode.

My tablet is Android 5.1

My desktop is the newest version of the Pro MLO.

This question is about the Android.

Everything seems to work fine.

But the problem is with starred items.

If I load a profile, tasks apoear under AllTasks.

If zi click on s task, all subtasks appear. But if I star it snd then look at starred items, yes the task appears, but when I click on the task, no subtasks.

Is this a limitation or do I need to do something?

Nick Clark

unread,
Dec 9, 2015, 5:09:27 AM12/9/15
to MyLifeOrganized
The All Tasks and Starred views are different types. The All Tasks is an Outline view showing everything including folders. The Starred view is an Action view, showing tasks that can be actioned, in this case filtered by those with a star set.

Nick

Andrei Bacean

unread,
Dec 10, 2015, 4:10:38 PM12/10/15
to MyLifeOrganized
Hi Edward
you can create a custom view to display the starred tasks with their children.
Filter by starred and enable the hierarchical view (check the Show Children checkbox).
Best regards
Andrei