Dear Experts,
We are buliding a gas plant. As EPCC and in order to optimize the extent of fire proofing application for the Pie racks structures as well as structural steel skids (supporting gas treatment vessels), I remember that for:
- Pipe racks fire proofing application is up to 3 m height from the pole base. Only the poles.
- Skids: Only saddles and their suppoting beams onthe skid
are subject to fire proofing.
Please share your experience in this field and applicable STD.
Thanks